Subs on Site
<Huskies> (3)
<G&M Woods> (2)
<Wall to Wall> (3)
<Clegg Steel> (5)
<Diamond Z> (3)
<Air Doctors> (3)
<Air Doctors> (3)
<Reliance> (5)
<DG Concrete> (3)
Work in Progress
(Huskies) Finished trenching around Building 'E' and started final grade.
(G&M) Installed Counter tops on the North tower of Building 'B'. Geary confirmed that we are missing short one upper cabinet above the stove for Building 'B'.
(Wall to Wall) Prepped the exterior of Building 'D'. Finished caulking the exterior siding.
(Clegg Steel) Installed the handrails on the stairs in Building 'B', cut down the Chimney caps, welded plates under the stairs, and fixed the stairs in Building 'D'
.
(Diamond Z) Finished the stone for the Club House and laid the brick for the Monument sign. It was way to small we decided to add 3 coarse on the top and fill it to the edge of the footing for length.
(Air Doctors) Worked on the flu vents for the furnaces and water heaters in Building 'B'.
(Reliance) Worked on the items from Building 'E' final inspection. Finished installing the devices on the South tower of Building 'B'.
(DG Concrete) Graded the North and West sides of Building 'B' for sidewalks and condensers