Monday 5/20/2013

Weather: Partly Cloudy/Rain 66˚/42˚   

Subs on Site
<Huskies>                        (3)
<Wall to Wall>                  (3)
<SBS>                              (2)
<Warburtons>                  (6)
<Nutek>                            (3)
<Sterns>                           (3)
<Reliance>                       (2)
<DG Concrete>                (3)

Work in Progress
(Huskies) Continued trenching around 'D'. 

(Wall to Wall) Masked and prepped the West Breezeway in Building 'C' for paint.

(SBS) Unloaded deliveries of blinds, mirrors, and Club House bathroom partitions.  I locked up Building 'D' and noticed that my construction key would not work on the doors.  I call Ryan (SBS) and he realized that he check each door in 'D' and 'E' with the unit keys, voiding the construction key.  He will trade the patio closet handle with the front handle 

(Warburtons) Worked on the top of the South end of Building 'B' as well as the entry on the South West corner.

(Nutek) Taped the Club House.

(Sterns) Formed for the sidewalks in front of Building 'D' & 'E'.

(Reliance) Pull out the temp power poles for the whole site.  Wired the last of the range hood cords.

(DG Concrete) Graded behind Building 'C' for sidewalks.







Sub Meeting 5/13/2013

Rob (Wall to Wall)
Rick (Warburtons)
Nate (Reliance)

Talking Points:
Clean-up: Clean your trash and organize your materials.
Rob (Wall to Wall) will ask about the 2nd crew for painting the exterior so they can continue touch up and paint the Club House while increasing the pace on the exteriors.
Building ‘A’ Car ports installed against the Building starts June 10th.
Building ‘C’  Re Final on Tuesday 5/21. Sidewalks formed Tuesday 5/21. Paint exterior complete this week.  Rain gutter starts 6/3.   HUD inspection Wednesday 5/22.
Building ‘D’  The Plumber cut holes in the bathrooms. The sheetrocker will have to patch this week.  Bob (Wall to Wall) Can paint this Friday and Saturday.
Building ‘E’  Carpet scheduled to start Thursday 5/23.  Sheetrock touch up can start now.  Bob (Wall to Wall) can paint this Friday and Saturday.
Building ‘B’  South tower countertop install starts Wednesday .  North Tower cabinets complete by 5/30. Grading starts Tuesday 5/21.  
Club House Drywall taping starts today complete Thursday 5/23.  
 
Schedule:
Building ‘C’
HUD inspection 5/22
Building ‘D’
Sheetrock touch up this week.
Paint touch up 5/24-5/25.
Final inspection 5/23.
Building ‘E’
Sheetrock touch up this week.
Paint touch up 5/24-5/25.
Final inspection 5/28.
Building ‘B’
South Tower Cabinets and Countertops installed 5/24.
North Tower Cabinets and Countertops installed 5/29.
Siding complete 5/28.
Backfill starts 5/21
Club House
Tape and texture complete 5/24.