Subs on Site
<Huskies> (3)
<G&M Woods> (2)
<Wall to Wall> (3)
<SBS> (3)
<Warburtons> (6)
<Nutek> (3)
<Sterns> (6)
<Reliance> (2)
<Red Oak> (2)
<DG Concrete> (3)
Work in Progress
(Huskies) Set more of the heads around 'D'. I met with Zac about the roof drain sumps and gravel in front of the patios. Zac agreed to install the sumps and the gravel in front of the patios if we provide the gravel. M13 will install gravel in the window wells.
(G&M) Installed the counter tops for the South tower of Building 'B'.
(Wall to Wall) Finished painting the exterior of Building 'C' and started prepping the exterior of Building 'D'.
(SBS) Installed blinds in Building 'B' and installed doors in the Club House.
(Warburtons) Finished the exterior of Building 'B'.
(Nutek) Textured the walls in the Club House and worked on the odds and ends as well as patched in Building 'D'.
(Sterns) Poured for the sidewalks behind Building 'E' & the 2nd 1/2 of the playground.
(Reliance) Started working on the trim in Building 'B' and items from Building 'D' final inspection.
(Red Oak) Continued running the gas lines to the furnaces and Water heaters for Building 'B'.
(DG Concrete) Graded the Southern end Building 'B' for sidewalks.
We had final inspection on Building 'D'.