Wednesday 5/15/2013

Weather: Partly Cloudy 83˚/51˚   Light rain 

Subs on Site
<Elite Structures>             (2)
<G&M Woods>                 (4)
<Huskies>                        (3)
<Wall to Wall>                  (3)
<Warburtons>                  (6)
<Clegg Steel>                  (3)
<Air Doctors>                   (4)
<Red Oak>                       (3)
<DG Concrete>                (3)

Work in Progress
(Elite Structures) Installed the last of their trim.  They told me that the layout for Building 'C's lot will not work.  They told me that we needed to move the handicap parking to the other side of the loading so that the columns will not be int he handicap stall. 

(G&M) Started install on the 3rd floor of South tower in Building 'B'

(Huskies) Continued trenching around 'D'. 

(Wall to Wall) Continued prep for Building 'C' exterior while they waited for paint delivery.  After lunch they started painting the trim on the North side of Building 'C' until the rain and wind forced them to stop.  Bob (Wall to Wall) finished painting A103 and A203 patches.

(Warburtons) Touched up and replaced trim on Building 'C' where they had left hammer marks.  Worked on the entry on the North end of Building 'B'.

(Clegg Steel) Repoured the concrete stairs that would not pass inspection.  They had missed 13 of the stairs on Building 'C' so I rented a jack hammer and Curtis, Mario and I jack hammered them out.  The concrete was in the truck on site for 2 hours and it came from Roosevelt.   

(Air Doctors) Installed ducts and furnaces in the North Tower Building 'B'. 

(Red Oak) Installed trim in Building 'E'.

(DG Concrete) Graded for sidewalks around the playground.and up to Building 'E'.

Dusty (Maeser Water) vacuumed around the two water meter cans for Building 'B' and will set the cans and meters tomorrow.