Subs on Site
<Huskies> (3)
<Wall to Wall> (3)
<SBS> (3)
<Warburtons> (6)
<Nutek> (4)
<Extreme Fire> (1)
<Sterns> (6)
<Reliance> (2)
<DG Concrete> (3)
Work in Progress
(Huskies) Continued trenching around 'D' and set their funny pipe.
(Wall to Wall) Painted the trim the West Breezeway in Building 'C' for paint. Painted the body of the exterior around the North and East side of Building 'C'.
(SBS) Installed blinds and mirrors in Building 'C' and stocked them in Building 'D'. Ryan traded the patio closet handle with the front handle in Building 'D' and 'E' so that our Construction Keys would work again.
(Warburtons) Worked on the top of the South end of Building 'B' as well as the entry on the South West corner.
(Nutek) Taped the breezeways in Building 'D' and fire taped the garages. Then started touch up in Building 'C'.
(Extreme Fire) Passed inspection on Building 'C' and 'D'. They had to cut the drywall in the Buildings to fix a couple heads.
(Sterns) Poured for the sidewalks in front of Building 'D' & 'E' and formed around the playground.
(Reliance) Pulled out the last temp power poles for the whole site. Wired the condensers on Building 'D'.