Subs on Site
<Huskies> (3)
<G&M Woods> (2)
<Wall to Wall> (3)
<SBS> (3)
<Warburtons> (6)
<Nutek> (3)
<Sterns> (6)
<Reliance> (2)
<Red Oak> (2)
<DG Concrete> (3)
Work in Progress
(Huskies) Final graded around 'D' and set some of the heads.
(G&M) Stocked the counter tops for Building 'B' installed the vanity tops and started on the kitchens on the South end of Building 'B'.
(Wall to Wall) Painted the trim the East Breezeway in Building 'C' for paint. Painted the body of the exterior around the West and half of the South side of Building 'C' until the wind was too fast to paint.
(SBS) Installed blinds and mirrors in Building 'D' and 'E'.
(Warburtons) Worked on the top of the North end of Building 'B' as well as the entry on the North West corner.
(Nutek) Textured the ceilings in the Club House and finished fire taping the garages.
(Sterns) Poured for the sidewalks behind Building 'D' & 1/2 of the playground.
(Reliance) Wired the condensers on Building 'E'. Pass inspection on the battery back up for the fire alarm in Buildings 'C' and 'D'.
(Red Oak) installed their water heaters in Building 'B' and started running the gas lines to the furnaces and Waterheaters.
(DG Concrete) Graded behind Building 'C' for sidewalks. Then moved behind Building 'B'.