Subs on Site
<Huskies> (3)
<Green Clean> (2)
<G&M Woods> (2)
<G&M Woods> (2)
<Wall to Wall> (3)
<Warburtons> (6)
<Diamond Z> (3)
<Nutek> (3)
<Nutek> (3)
<Sterns> (6)
<Air Doctors> (3)
<Reliance> (5)
<DG Concrete> (3)
Work in Progress
(Huskies) Started trenching around Building 'E'.
(G&M) Installed cabinets in all but one of the units on North tower of Building 'B'. Greay told me that we might be short one upper cabinet above the stove for Building 'B'. He will check tonight and let me know for sure in the morning.
(Wall to Wall) Prepped the exterior of Building 'D'. Their brand new paint sprayer burned up it mother board. Rick (Warburtons) called to tell me that the painters need to caulk the siding were it butts against the trim but should not caulk the butt joints in the field. I checked on the Hardi web site and confirmed it. I told Rob (Wall to Wall) he will have to caulk all of the siding were it butts the trim, and he told me that it will take over a week per 16 plex and 2 weeks for a 32.
(Warburtons) Finished the last of the breeze ways on Building 'B'. We walked the job and I gave them a touch up list. They filled the 30 yrd dumpster with siding a pallets.
(Diamond Z) Worked on the stone for the Club House.
(Nutek) Finished the patches in Building 'E' including the fire tape in the under the stair closets.
(Sterns) Poured for the sidewalks behind and to the East of Building 'E'. I asked them to get the stairs in front of Building 'E' formed and poured.
(Reliance) Worked on the trim in Building 'B' and items from Building 'E' final inspection. They used our Back hoe and dug the trench and laid the conduit for the South East monument sign.
(DG Concrete) Graded the East end Building 'B' for sidewalks and condensers
We had final inspection on Building 'E'. The Building was not ready. Every furnace was open and the condencer lines were not run. The inspector found water on the floor in the laundry room on E102 which we discovered was coming from a leak in D302. Aaron (Inspector) told me that we almost got a $50 re inspection fee because there was a note on every unit.