Subs on Site
<Huskies> (5)
<Green Clean> (2)
<Wall to Wall> (4)
<Reliance> (2)
<Red Oak> (2)
<Sterns> (7)
Work in Progress
(Huskies) Started trenching around the Clubhouse.
(Green Clean) Rough clean of Building 'B'.
(Wall to Wall) Touched up Building 'C' and 2nd coated the steel columns.
(Reliance) Installed trim in the Club House. They had a couple lenses that broke that they reordered.
(Red Oak) Worked on the water heater drains and strapping the gas lines. They also worked on their clean up.
(Sterns) Poured behind Building 'B'. Mark told me that they will no longer leave areas un poured for the lift access. He also said they are going to just pour according to their schedule. I told him about the LD's and asked him if there would be anyway they could get the access to the Building poured tomorrow. He said they would try to get more help tomorrow so they can pour 30 yrds and make it happen.