Thursday 6/23/2013

Weather: Sunny  87˚/52˚

Subs on Site
<Huskies>                        (5)
<Wholesale Flooring>      (2)
<Wall to Wall>                  (3)
<Sterns>                         (9)

Work in Progress
(Huskies) Started laying sod around Building 'A'.

(Wholesale Flooring) Finished laying tile in the ClubHouse and started grouting. 

(Wall to Wall) Rob showed me how much better the decks would look if he painted the concrete on the face of the them.  He went through and painted the faces on all of the painted buildings.  Bob started the final touch-up on Building 'B'.

(Sterns) Poured around the ClubHouse.

The painter told me that a few of the bolts on the steel were now loose.  He let Mario use the lift and tighten them.

We received delivery of the wood chips in the playground.