Tuesday 6/18/2013

Weather: Sunny  89˚/52˚   

Subs on Site
<Huskies>                        (5)
<Green Clean>                (2)
<Wholesale Flooring>      (3)
<Wall to Wall>                  (4)
<Reliance>                       (2)
<Clegg Steel>                   (4)
<Red Oak>                     (5)
<Sterns>                         (9)

Work in Progress
(Huskies) Final grade around the Clubhouse.

(Green Clean) Started cleaning the floors in Building 'B'.

(Wholesale Flooring) Started laying tile.  They will have a wainscot in the bathrooms.

(Wall to Wall) Touched up Building 'D&E' and 2nd coated the steel columns.

(Reliance) Worked on odds and ends for the garages and temp power.

(Clegg Steel) Fixed the stairs on the inspection list and installed the dumpster gates.

(Red Oak) I started making a punch list for them.  The first 4 units had 2 or 3 items each.  I called Jake and he did not answer.  I went to their house and Ether was there.  I spoke with them and they all came and started their own punch list.

(Sterns) Poured in front and South of Building 'B'.   They also poured the North West corner in the back of the Building so that we will have access to the Building for inspection.