Weather: Sunny 87˚/52˚
Subs on Site
Subs on Site
<Huskies> (5)
<Green Clean> (2)
<Wholesale Flooring> (2)
<Wall to Wall> (3)
<Red Oak> (2)
<Sterns> (9)
Work in Progress
(Huskies) Final grade around the Clubhouse.
(Green Clean) Continued cleaning the floors in Building 'B'.
(Wholesale Flooring) Continued laying tile in the ClubHouse. They will have a wainscot in the bathrooms.
(Wall to Wall) Touched up Building 'D&E' and 2nd coated the steel columns.
(Red Oak) Caulked the water heater drain lines were they came out of the siding. They also work on some punch list items for C and E.
(Sterns) Poured the last section of concrete on Building 'B' before the inspector got here to finish the final inspection. inspection. They did not pour an ADA ramp for the club house so they tore out a section of curb and poured one in.
The neighbor came over very upset. She said that she prayed every day that Building 'C' would burn down. The painter had hit her fence on Monday morning. I went from lift to lift to find the one that had hit it. When I confronted Rob (Wall to Wall) he told me he had forgotten to tell me. Mario and Rob took the backhoe and bent it back strait. Rob spoke with the neighbor and smoothed it over.
HUD gave us our PTO on Building 'B'.
The neighbor came over very upset. She said that she prayed every day that Building 'C' would burn down. The painter had hit her fence on Monday morning. I went from lift to lift to find the one that had hit it. When I confronted Rob (Wall to Wall) he told me he had forgotten to tell me. Mario and Rob took the backhoe and bent it back strait. Rob spoke with the neighbor and smoothed it over.
HUD gave us our PTO on Building 'B'.