Weather: Sunny 51˚/28˚
Subs on Site
<Cardalls> (2)
<Nutek> (5)
<Warburtons> (4)
<Standard Builders> (3)
<Diamond Z> (7)
<Air Doctors> (4)
<Reliance> (11)
<Utek> (17)
<Red Oak Plumbing> (7)
<DG Concrete> (2)
Work in Progress:
(Cardalls) started insulating pre rock areas of the last 6 of 8 units on Building 'A' 1st floor
(Nutek) sheet rocked the pre-rock areas of the first 2 of 8 units on Building 'A' 1st floor
(Warburtons) Started shingling Building 'A'
(Standard Builders) installed the metal door frames in the under stair closets on Building 'A' and the patio closets on 1st floor of Building 'C'
(Diamond Z) started laying stone on Building 'A'
(Air Doctors) worked on the exhaust fans for the first floor of Building 'C'.
(Reliance) pulled wire on Building 'A' second floor and started boxing on 3rd floor. They also added outlets for the units on 1st floor were the sliding doors were on the wrong side.
(Utek) finished standing the walls on Building 'C' 3rd floor and started setting sections of 4th floor.
(Red Oak Plumbing) finished the vents and worked on the water lines for the 2nd floor of Building 'A'
(DG Concrete) stacked the rock wall on the East side of center section of Building 'A'
Sub Meeting 11/19/2012
Pablo (Extreme Fire)
Jesse (Diamond Z)
William (Air Doctors)
Shad (DG Concrete)
Bryson (Reliance)
Jesse (Utek)
Talking Points
- Dumpster is for Utek trash only. I must police this and you will be back charged if you use it.
- We will be striping the parking lot this week. No parking around Building ‘A’. Park off pavement.
- Building Clean-up. All sub must clean after themselves. No cups, no trash in the Building. Reliance cleaned up after all subs on the 2nd floor. Thank you, Bryson.
- We cannot finish the rock walls on Building ‘C’ without closing off access for lifts on the entire North side.
- We need to stub out for the sidewall heads in each patio before stone and siding.
- Air Doctors would like to have the drops framed before the run their ducts. They will install their hard duct then we will frame the drops
Schedule
Pre-Rock
2nd Floor Tuesday 11/20
3rd Floor Tuesday 11/27
4th Floor Thursday 11/29
Final 4-way
1st Floor Tuesday 11/27
2nd Floor Friday 11/30
3rd Floor Thursday 12/6

