Friday 11/16/2012

Weather: Sunny 49˚/24˚

Subs on Site
<Warburtons>               (4)
<Diamond Z>                 (5)
<Air Doctors>                (4)
<Reliance>                    (4)
<Utek>                          (22)
<Red Oak Plumbing>     (7)
<DG Concrete>             (2)

Work in Progress:
(Warburtons) Dried in all three garages 

(Diamond Z)Started scratch coat on Building 'A'.  We did not have a hose addapter for the hydrant meter so I had to run and buy one.

(Air Doctors)touched up the fire caulking and worked on the vents in the attic.

(Reliance) Continued pulling wire on 2nd Floor.

(Utek) Set wall sections for Building 'C' 3rd Floor,  Started pre-fab on Building 'C' 4th floor. Continued pre-fab on Building 'B' wall sections

(Red Oak Plumbing) fire caulked the fire sprinkler pipes for the 1st and 2nd floors of Building 'A' and finished vents through the roof.