Tuesday 11/20/2012

Weather: Sunny 50˚/25˚

Subs on Site
<Cardalls>                     (2)
<Nutek>                         (7)
<Warburtons>               (3)
<Diamond Z>                 (7)
<Extreme Fire>              (5)
<Air Doctors>                (4)
<Reliance>                    (11)
<Utek>                          (22)
<Red Oak Plumbing>     (7)
<DG Concrete>             (2)

Work in Progress:
(Cardalls)Insulated all the walls on the 1st Floor for Building 'A' and met with Corey Coleman (IECC) their process is approved as long as they foam the penetrations.  They will run out of Ceiling insulation tomorrow and will let me know as soon as they can get more up here.

(Nutek) Sheet rocked the pre-rock areas on 1st floor.

(Warburtons) wrapped house wrap around the Southern 1/3 of Building 'A'.  Aaron (Uintah County) would like them to tape all seams not just around the penetrations.

(Diamond Z) continued to put stone on the Southern end of Building 'A'.  Jesse noticed that the columns above the entry gables do not have flashing.  They well cut their gray coat up 6" so that Warburtons can install the flashing on Monday.

(Extreme Fire) worked on the 1st floor of Building 'C' as well as the sidewall sprinklers for the decks and closets on the 1st floor of Building 'A'.  They also started the attic section on Building 'A' 

(Air Doctors) installed the exhaust vents on the 1st floor of Building 'C'

(Reliance) pulled wire on 3rd floor Building 'A'.

(DG Concrete) finished the rock walls for Building 'A' and started spreading road base for the sidewalks.