Thursday 11/15/2012


Weather: Sunny 44˚/24˚

Subs on Site
<Warburtons>               (4)
<Diamond Z>                 (5)
<Air Doctors>                (4)
<Reliance>                    (4)
<Utek>                          (22)
<Red Oak Plumbing>     (7)
<DG Concrete>             (2)

Work in Progress:
(Warburtons) dried in Building 'A"

(Diamond Z) Finished the lath and tar paper on the East side of Building 'A'.and passed inspection.

(Air Doctors) finished the vent pipes out of the chimney 

(Reliance) Continued pulling wire on 2nd Floor.

(Utek) Sheeted the 3rd floor of Building 'C'. Stocked the wall sections for Building 'C' 3rd Floor,  Installed fire stop and draft stop in Building 'A' first floor demising wall floor section..   

(Red Oak Plumbing) finished the gas lines on the 1st and 2nd floors on the South End of Building 'A' and Fire caulked for inspection..

(DG Concrete) Built rock wall on the West side of Building 'A'.