Subs on Site
<Warburtons> (4)
<Standard Builders> (3)
<Diamond Z> (5)
<Air Doctors> (4)
<Reliance> (4)
<Utek> (22)
<Red Oak Plumbing> (7)
<DG Concrete> (2)
Work in Progress:
(Warburtons) dried in Building 'A"
(Standard Builders) Installed the last 10 exterior door frames. All of Building 'A' is done except for the under stair closest.
(Diamond Z) Finished the lath an tar paper on the West side of Building 'A' then started around the North end.
(Air Doctors) finished the vent pipes on the 4th floor through the trusses
(Reliance) started pulling wire on 2nd Floor.
(Utek) Set more floor sections on 3rd floor of Building 'C'. Finished all pick-up in Building 'D' & 'E' 1st and 2nd floors, Trusses for Building 'C' delivered. Installed fire stop and draft stop on in all double exterior walls.
(Red Oak Plumbing) finished the gas lines on the 1st and 2nd floors on the North End of Building 'A'.