Subs on Site
<Cardalls> (2)
<Warburtons> (3)
<Diamond Z> (7)
<Extreme Fire> (5)
<Air Doctors> (4)
<Reliance> (11)
<Utek> (22)
<Red Oak Plumbing> (7)
<DG Concrete> (2)
Work in Progress:
(Cardalls)Insulated all the ceilings on the 1st Floor for Building 'A'
(Warburtons) finished taping the joints of their house wrap and started up the West side.
(Diamond Z) work on the stone on the South End of Building 'A'
(Extreme Fire) Worked on the sidewalls for the South end of Building 'A' and the attic system. They also installed the sprinklers for the first floor of Building 'C'. While drilling for the attic system riser the drilled a TJI on each floor (See picture below)
(Air Doctors) started building the hard duct on the first floor of Building 'A'.
(Reliance) started wiring the 4th floor of Building 'A'.
(Utek) stood the walls on the 4th floor of Building 'C' and continued the pre-fab of the roof sections for Building 'C'.
(Warburtons) finished taping the joints of their house wrap and started up the West side.
(Diamond Z) work on the stone on the South End of Building 'A'
(Extreme Fire) Worked on the sidewalls for the South end of Building 'A' and the attic system. They also installed the sprinklers for the first floor of Building 'C'. While drilling for the attic system riser the drilled a TJI on each floor (See picture below)
(Air Doctors) started building the hard duct on the first floor of Building 'A'.
(Reliance) started wiring the 4th floor of Building 'A'.
(Utek) stood the walls on the 4th floor of Building 'C' and continued the pre-fab of the roof sections for Building 'C'.