Tuesday 11/27/2012

Weather: Sunny 48˚/21˚

Subs on Site
<Cardalls>                     (2)
<Warburtons>               (12)
<Diamond Z>                 (3)
<Extreme Fire>              (3)
<Air Doctors>                (4)
<Utek>                          (19)
<Red Oak Plumbing>     (2)

Work in Progress:
(Cardalls)Insulated all the ceilings on the 2nd Floor for Building 'A'.

(Warburtons) installed siding on the Southern end of Building 'A'.  Installed house wrap on the West and East side of the center section.  Roofed the East side.

(Diamond Z) installed the Stone on the North West corner of Building 'A'.

(Extreme Fire) worked on the attic system for Building 'A'


(Air Doctors) finished Installing the Hard ducts on Building 'A' 1st floor.

(Utek) Repaired the crane cable and started setting trusses on Building 'C'.  Continued pre fabing floor sections for Buildings 'D' and 'E'. Started the Club House.

(Red Oak Plumbing) finished and passed off the gas for the 3rd and 4th floors of Building 'A' and started on the water lines.  They also started drilling holes for the gas and drain on Building 'C'