Thursday 2/28/2013


Weather: Sunny  30˚/12˚ 

Subs on Site
<Wholesale Flooring>      (7)
<SBS>                              (8)
<Diamond Z>                    (2)
<Nutek>                            (11)
<Sterns>                           (3)
<Extreme Fire>                 (4)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Red Oak Plumbing>       (6)


Work in Progress
(Wholesale Flooring) Installed carpet on the 3rd floor of Building 'A' and tack strip and pad on 4th floor.  I walked into one of the 2x2 units and noticed that the entry vinyl had a weird angle on it.  Lance and I discussed it and what the easiest fix would be as well as how much work it would take.  I called Nick and he confirmed that we needed to change   it.

(SBS) Trimed in the units on the East side of the 3rd floor of Building 'C', worked on hardware and unboxed all of the appliances for Building 'A'. 

(Diamond Z) Continued to lay stone on the South West side of Building 'E'.
(Nutek) Sanded the texture in West tower 4th floor of Building 'C'.  Hung drywall pre-rock on the 1st floor of Building 'E'.  Taped the 2nd floor of Building 'D'

(Sterns) Poured the dumpster pad and both of the temporary ramps to Building 'A'.

(Extreme Fire) Worked on Building 'B's attic system.  Passed inspection on Building 'B' plastic system. Tried a flow test  during our Fire alarm inspection but the underground was frozen and did not flow enough.   
.
(Warburtons) Worked on the North side of Building 'C' and the 4th floor East breezeway.  They started on the South side of Building 'D'

(Air Doctors) Installed trim on the North Tower of Building 'A'.  Started the Hard ducts on 1st floor Building 'E' . 

(Reliance) Installed the parking lot lights for Building 'A'.  Programmed the fire alarm system and passed inspection for Building 'A'.

(Red Oak) Finished Installing trim on the South tower Building 'A' and started on the North tower.  They also started running gas on the Club House.









Wednesday 2/27/2013

Weather: Sunny  28˚/4˚ 

Subs on Site
<Wholesale Flooring>      (7)
<Wall to Wall>                  (4)
<SBS>                              (4)
<Diamond Z>                    (2)
<Nutek>                            (11)
<Cardalls>                        (3)
<Extreme Fire>                 (1)
<Clegg Steel>                   (7)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (5)
<Red Oak Plumbing>       (4)


Work in Progress
(Wholesale Flooring) Installed carpet on the 2nd floor of Building 'A' and tack strip and pad on 3rd floor.

(Wall to Wall) Painted units on 2nd floor Building 'C'.

(SBS) Trimed in the units on the West side of the 4th floor of Building 'C' and worked on hardware in Building 'A'.

(Diamond Z) Started laying stone on South West side of Building 'E'.

(Nutek) Textured the West tower 4th floor of Building 'C'.  Hung drywall on the 3rd floor of Building 'D'.

(Cardalls) Insulated the fire riser rooms in 'C', 'D', and 'E' and installed baffles on the patios in Building 'C' and 'D'

(Extreme Fire) pumped the pressure on the fire sprinklers on Building 'A' to 200 lbs.  We checked each unit while the system filled.  The stocked the pipe for and worked on Building 'B's attic system.   
.
(Clegg Steel) Worked on the stairs for Building 'B'.  Installed the deck rails and hand rails on Building 'A'.


(Warburtons) Worked on the North side of Building 'C' and the 4th floor East breezeway..

(Air Doctors) Installed flex ducts on the 4th floor in Building 'D'.  Installed trim on the North Tower of Building 'A'.  Finished their vent pipes one of the chimney caps. 

(Reliance) Worked on the last 4 units North tower trim. Wired the fans and lights in the drops on 4th floor Building 'D' 

(Red Oak) Installed trim on the South tower Building 'A'




Tuesday 2/26/2013

Weather: Sunny  30˚/13˚ 

Subs on Site
<Wholesale Flooring>      (7)
<Wall to Wall>                  (4)
<SBS>                              (4)
<Diamond Z>                    (2)
<Nutek>                            (11)
<Cardalls>                        (3)
<Extreme Fire>                 (1)
<Clegg Steel>                   (7)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (5)
<Red Oak Plumbing>       (4)


Work in Progress
(Wholesale Flooring) Installed vinyl on 1st floor of Building 'C' and started tackstrips and pad on 2nd floor of Building 'A'

(Wall to Wall) Primed units on 2nd floor Building 'C'.

(SBS) Trimed in the units on the West side of the 3rd and 4th floors of Building 'C'.

(Diamond Z) Laid stone on the South East Corner of Building 'D'

(Nutek) Textured the West tower 4th floor of Building 'C'.  Hung drywall on the 3rd floor of Building 'D'.

(Cardalls) Finished insulation on 4th floor of Building 'E'.

(Extreme Fire) Turned on the water to the fire sprinklers on Building 'A'.  We checked each unit while the system filled.  We found 4 head that were popped.  Only one of which dripped very much water.  We vacuumed out the water.
.
(Clegg Steel) Worked on the stairs for Building 'B'.  Installed the deck rails and hand rails on Building 'A'.  They set the chimney caps on the roof of Building 'A' but Air Doctors needed to run the vents out before they could set them.
One of the stair sections for Building 'B' was frozen to the ground and when Rob (Clegg Steel) tried to lift it and snapped the knuckle on our lift. 


(Warburtons) Worked on the North side of Building 'C' and the 4th floor West breeze way and 3rd floor of the East breezeway..

(Air Doctors) Installed flex ducts on the 3rd floor in Building 'D'.  Installed trim on the 4th floor South Tower of Building 'A'.  Finished their vent pipes one of the chimney caps. 

(Reliance) Worked on the last 4 units North tower trim. Wired the fans and lights in the drops on 3rd and 4th floor Building 'D' 

(Red Oak) Installed water lines in Building 'B' and started trim on the South tower Building 'A'






Monday 2/25/2013

Weather: Sunny  29˚/5˚ 

Subs on Site
<Wall to Wall>                  (3)
<SBS>                              (3)
<Diamond Z>                    (2)
<Nutek>                            (8)
<Cardalls>                        (3)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (5)
<Red Oak Plumbing>       (2)


Work in Progress
(Wall to Wall) Prepped 6 units on 2nd floor Building 'C'.

(SBS) Arrived at 5 pm after having fuel pump problems and stocked trim in the units on the West side of the 3rd and 4th floors of Building 'C'.

(Diamond Z) Started laying stone on Building 'D's South West corner.

(Nutek) Textured the 1st floor of Building 'D'.  Hung drywall on the 2nd floor of Building 'D'.

(Cardalls) Finished insulation on 3rd floor Building 'E' and worked on 4th floor.

(Warburtons) Worked on the North side of Building 'C' and the 4th floor West breeze way and 2nd floor of the East breezeway..

(Air Doctors) Installed flex ducts on the 3rd floor in Building 'D'.  Installed trim on the 3rd floor South Tower of Building 'A'. 

(Reliance) Worked on the last 4 units North tower trim. Wired the fans and lights in the drops on 3rd and 4th floor Building 'D' 

(Red Oak) Installed water lines in Building 'B' and started trim on the South tower Building 'A'





Sub Meeting 2/25/2013

Rick (Warburtons)
Bryson (Reliance)
William (Air Doctors)
Ether (Red Oak)
Rob (Wall to Wall)
Sean (Extreme Fire)

Talking Points:
Track out and Mud: Each contractor is responsible for their own track out both into the street and onto our lot.  I will look into getting some gravel for a track out.
Heaters: I asked that only the foremans, who know of the fire sprinkler problem, can touch the heaters we have already had heaters in Building ‘C’ turned too high.
Building ‘A’ Red Oak has not started his trim in Building ‘A’.  Air Doctors still needs to trim 3rd and 4th floors on the South Tower.  Reliance has the South Tower units complete in Building ‘A’ they should have the last 4 units on the North Tower today.  Reliance will need a couple days next week to install the light poles and corridor lights and signs.  Bryson is concerned that the conduits may have ice in them.  Unit 405’s main breaker is tripped,  Bryson will attempt to locate the area were the main feeder got hit and determine if it is a trim nail or siding.  The block-outs for the lights in corridors are correct but the exit sign blocks need to be fixed. Rick (Warburtons) told Bryson (Reliance) to let Jose (Warburtons) know again and they would get them fixed.  Carpet will be installed tomorrow 2/26 on the 1st floor and then as close as they can chase the plumbing trim on 2nd.  When the carpet is installed he can touch up Building ‘A’ on Friday.  The kickers are still on the roof and in the chimneys on Building ‘A’ Rick (Warburtons) said they will get them down this week.  Sean (Extreme Fire) needs to get water in the sprinkler system for Building ‘A’.  The sooner the better, if there is any leaks at all will make a big problem bigger if the carpet is installed.
Building ‘C’ Vinyl will be installed on 1st floor tomorrow 2/26.  Ryan (SBS) had car problems and did not make it up here this morning he will have 3rd floor on the West tower ready for paint by the end of the day on 2/26..  Rob (Wall to Wall) said they will finish paint on all 2nd floor and the 3rd floor West tower this week and finish the building next week.  (G&M Woods) will start cabinet install on Wednesday 2/27.
Building ‘D’ 1st floor was textured today.  2nd floor should be textured by 3/5.  Gypcrete will be poured on Thursday 2/28.  William (Air Doctors) Said that they will have the 3rd floor complete for Nutek in the morning.  The Corridors will be formed this week and if possible poured Friday 3/1.  Siding will start in 2 weeks.

Building ‘E’  Insulation will be complete by the end of the day Tuesday 2/26.  Sheetrock will be stocked today and tomorrow.  
Building ‘B’  Ether (Red Oak) will be ready for DWV on Tuesday 2/26.  Bryson (Reliance) said that they need a week to finish the back of house install and then they will be able to wire 4 units per day from there on out.  


Schedule:
Building ‘A’
Carpet 1st floor  2/26

Final inspection 3/5
Building ‘C’
2nd floor Paint started 2/25
1st floor Vinyl 2/25
2nd floor finish work complete 2/19
West side 3rd floor Texture complete by 10 am 2/20
East side 4th floor Texture complete end of day 2/20
Building ‘D’
1st floor drywall taped 2/26
2nd floor Drywall hung.
3rd floor ducts and fans complete 2/26

3rd floor drywall hung 2/27.
4th floor ducts complete 2/27
4th floor drywall hung 3/1
Building ‘E’
Insulation complete 2/26
Pre Rock on 1st floor starts Wednesday 2/27

Friday 2/22/2013


Weather: Partly Cloudy  28˚/12˚ 

Subs on Site
<G&M>                             (2)
<Wall to Wall>                  (3)
<SBS>                              (2)
<Nutek>                            (11)
<Cardalls>                        (5)
<Warburtons>                  (11)
<Utek>                              (2)
<Air Doctors>                   (2)
<Reliance>                       (5)
<Red Oak Plumbing>       (2)


Work in Progress
(G&M) Cut holes for sinks in the last of Building 'A' units.

(Wall to Wall) Striped and cleaned 1st floor Building 'C'.

(SBS) Installed hardware in the North Tower Building 'A'.

(Nutek) Sanded East side 4th floor of Building 'C'.  Hung the drops on one unit in Building 'D'.  Textured the paitos in Building 'A'.

(Cardalls) Insulation on 3rd floor Building 'E' and started on 4th floor.

(Warburtons) Worked on the North side of Building 'C' and the 4th floor West breeze way.

(Utek) Framed drops on Building 'D' 2nd and then 3rd floors.

(Air Doctors) Installed flex ducts on the 2nd floor in Building 'D'.  Installed furnaces on the North Tower of Building 'A'. 

(Reliance) Worked on the North tower trim. Wired the fans and lights in the drops on 2nd floor Building 'D' 

(Red Oak) Installed water lines in Building 'B' and started trim on the South tower Building 'A'  


Thursday 2/21/2013


Weather: Partly Cloudy  30˚/10˚ 

Subs on Site
<Wall to Wall>                  (3)
<Nutek>                            (11)
<Cardalls>                        (7)
<Warburtons>                  (11)
<Utek>                              (2)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Red Oak Plumbing>       (2)


Work in Progress
(Wall to Wall) Painted first floor Building 'C'.

(Nutek) Textured East side 4th floor of Building 'C'. 

(Cardalls) Insulation on 3rd floor Building 'E'.

(Warburtons) Worked on the North side of Building 'C' and the 4th floor West breeze way.

(Air Doctors) Installed hard ducts on the 4th floor in Building 'D'.  Installed furnaces on the North Tower of Building 'A'. Started flex ducts on one unit 2nd floor of Building 'D'

(Reliance) Worked on the North tower trim.  Unit 405's main breaker is tripping.  Bryson is going to investigate tomorrow. 

(Red Oak) Installed water lines in Building 'B'.  

Wednesday 2/20/2013


Weather: Partly Cloudy  34˚/16˚ 

Subs on Site
<G&M>                             (6)
<Wall to Wall>                  (3)
<SBS>                              (3)
<Nutek>                            (11)
<Cardalls>                        (7)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Red Oak Plumbing>       (6)


Work in Progress
(G&M) Stocked the cabinets in Building 'C'.  The painters already had the doors spread in on the 1st floor and did not have enough room for cabinets.  G&M stocked the 1st floor cabinets in the garages and labeled them so that my labor can move them into the units tomorrow after the 1st floor is painted.


(Wall to Wall) Primed and Painted first floor Building 'C'.

(SBS) Installed the laundry doors on 2nd floor Building 'C'.  Installed hardware on the South tower Building 'A'

(Nutek) Textured West side 4th floor of Building 'C'. 

(Cardalls) Insulation on 2nd floor Building 'E' and blew in the insulation on Building 'C'

(Warburtons)  Worked on their pump jacks on North center of Building 'C' up to the soffit and in the West Breeze way and patios up to 4th floor and started on the East Breezeway.

(Air Doctors) Installed hard ducts on the 3rd floor in Building 'D'.  Mario and Curtis had to finish and touch up their fire caulk on 3rd and 4th floors Building 'E'.  

(Reliance) Tested out the 4th floor units on the South tower of Building 'A'.  Started on the North tower.

(Red Oak) Installed tubs and water lines in Building 'B'.  They finished stocking trim for Building 'A'.






Tuesday 2/19/2013


Weather: Partly Cloudy  31˚/17˚ 

Subs on Site
<Wall to Wall>                  (3)
<Diamond Z>                    (4)
<SBS>                              (3)
<Nutek>                            (11)
<Cardalls>                        (7)
<Warburtons>                  (9)
<Extreme Fire>                 (1)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Red Oak Plumbing>       (6)


Work in Progress
(Wall to Wall) Prepped first floor and 1/2 of 2nd floor Building 'C'.

(Diamond Z) Passed lath inspection and scratched Building 'E'

(SBS) Installed the laundry doors on 1st floor.  Installed hardware on the South tower Building 'A'

(Nutek). Textured West side 3rd floor of Building 'C'.  Taped the pre Rock and lid on 4th floor Building 'D'.  Taped the last of the drywall behind the tubs on Building 'B'.

(Cardalls) Finished insulation on 1st floor Building 'E' and blew in the insulation on Building 'C'

(Warburtons)  Worked on their pump jacks on Building 'C' finishing both ends up to the soffit and in the West Breeze way and patios up to 4th floor..

(Extreme Fire) Cut the sprinkler heads for Building 'D' 2nd floor and worked on the details in Building 'A'

(Air Doctors) Installed flex ducts on 1st floor and worked hard ducts on the 3rd floor in Building 'D'.  Finished fire caulk on 3rd and 4th floors Building 'E', inspection moved to Wednesday.  

(Reliance) Installed trim on the West tower of Building 'A'.  The inspector noted that the panels did not have GFCI breaker for our temp outlet.  Jared said he could switch them out.

(Red Oak) Installed tubs and DWV in Building 'B'.  They also had the trim for Building 'A' delivered..





Monday 2/18/2013


Weather: Partly Cloudy  27˚/8˚ 

Subs on Site
<Wall to Wall>                   (2)
<Diamond Z>                    (4)
<SBS>                              (2)
<Nutek>                            (11)
<Cardalls>                        (5)
<Warburtons>                  (9)
<Extreme Fire>                 (2)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Red Oak Plumbing>       (6)


Work in Progress
(Wall to Wall) Prepped 4 units on the 1st floor Building 'C'.

(Diamond Z) Finished Lathing Building 'E'

(SBS) Installed trim in 2nd floor Building 'C'. The laundry doors were not on site and were not installed.  John (Top Notch) said the would be on site tomorrow morning so that Ryan could install them before Wall to Wall painted.

(Nutek). Taped on the West side 3rd floor and 4th floor of Building 'C'.  Hung the pre Rock and lid on 4th floor Building 'D' Hung the last of the drywall behind the tubs on Building 'B'.

(Cardalls) Started insulating 1st floor Building 'E'

(Warburtons)  Worked on their pump jacks on Building 'C' and in the West Breeze way and patios.

(Extreme Fire) Cut the sprinkler heads for Building 'D' 1st floor and worked on the details in Building 'A'

(Air Doctors) Worked hard ducts on the 2nd floor in Building 'D'  Hung the flexible ducts on the 1st floor of Building 'D'.

(Reliance) Installed trim on the West tower of Building 'A'.

(Red Oak) Installed tubs and DWV in Building 'B'.





Sub Meeting 2/11/2013

Rick (Warburtons)
Doug (Cardalls)
Eric (Nutek)
Bryson (Reliance)
William (Air Doctors)
Ether (Red Oak)
Rob (Wall to Wall)

Talking Points:
I asked everyone to clean up their work area and even just a little more so that the sight does not look like a dump.
Building ‘A’ final inspection is on 2/27.  Reliance will have the South tower 1st - 4th floors will be trimmed out today. Reliance will have the remainder Building ‘A’ units complete this week, they will need a couple days next week to install the light poles and corridor lights and signs.  The block-outs for the lights in corridors are correct but the exit sign blocks need to be fixed. Rick (Warburtons) told Bryson to let Jose (Warburtons) know and they would get them fixed.   Plumbing trim will be delivered Tuesday 2/19 and Ether thought they would need through the weekend to trim the South tower.  He would also would like to have the building secure.  I asked Ether (Red Oak) to get the furnaces on the South end of 2nd floor Building ‘A’ hooked to the gas so that we can use the heaters.
Building ‘C’ The laundry room doors are not on site.  John (Top Notch) said they will be delivered tomorrow morning.  Ryan (SBS) said that if they are here by noon 1st and 2nd floors will be hung by the end of the day.  Rob (Wall to Wall) said that will work so that they do not have to come back to prime.  Ether asked to put water heaters in the units in box Rob (Wall to Wall) said that would not be a problem.
Building ‘D’ gypcrete will be poured on Thursday 2/28.  Fire caulk inspection will be tomorrow morning for 1st and 2nd floors.  The framers will be here on Wednesday and will frame the drops at a rate of  ½ day per floor.  Air Doctors will be able to stay ahead of them.  Nutek will be able to hang one floor per day.
Building ‘E’ 4 way inspection for 3rd and 4th floors will be on Tuesday 1/19 because today is a holiday.  Insulation on 1st floor will be complete by the end of the day Tuesday 1/19 so that Nutek can hang the pre rock.
Building ‘B’ Nutek finished pre Rock behind the tubs and cases in Building B today and will tape them tomorrow..  Ether (Red Oak) hung some of the units this weekend so that they could continue setting the tubs.  They will be ready for DWV on Thursday 2/21.


Schedule:
Building ‘A’
Carpet West tower 2/25

Final inspection 2/27
Building ‘C’
1st floor Paint started 2/18
1st floor and 4 units on 2nd floor Vinyl 2/25
2nd floor finish work complete 2/19
West side 3rd floor Texture complete by 10 am 2/20
East side 4th floor Texture complete end of day 2/20
Building ‘D’
1st floor drywall hung 2/20
2nd floor hard ducts and line sets Tuesday 2/19 drops the next day.
3rd floor hard ducts and line sets Wednesday  2/20 drops the next day.
4th floor hard ducts and lines sets Thursday 2/21 drops the next day.
Building ‘E’
4-way inspection 3rd and 4th floor 2/18
Insulation starts 2/18 1st floor.
Pre Rock on 1st floor starts Wednesday 2/20