Wednesday 2/13/2013


Weather: Hazy/Partly Cloudy  23˚/10˚ 

Subs on Site
<Diamond Z>                    (4)
<SBS>                              (2)
<Nutek>                            (8)
<Warburtons>                  (9)
<Extreme Fire>                 (2)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Utek>                              (3)
<Red Oak Plumbing>       (3)


Work in Progress
We passed 4-way for Building 'E' 1st and 2nd floor except for unit 101 which had 10 locations that the plumber needed to fire caulk.  We passed the gas lines on the South end of Building 'B'

(Diamond Z) Finished Lathing Building 'D'

(SBS) Stocked doors and delivered trim in 1st floor Building 'C'.  Continued hanging the patio closet doors.

(Nutek). Taped on the West side 3rd floor and 4th floor of Building 'C' and hung the 4 units on the West end 4th floor then started the East units. 

(Warburtons) worked on the details around Building 'A'. Worked on the roof on Building 'D'. Worked on their pump jacks on Building 'C' and in the West Breeze way.

(Extreme Fire) Worked on the attic system for Building 'E'

(Air Doctors) Worked hard ducts on the 2nd floor in Building 'D'  Hung the flexible ducts on the last 2 units on 4th floor of Building 'C'.

(Reliance) Pulled wire on Building 'E' 

(Utek) Built the drops on 1st floor of Building 'D'

(Red Oak) Worked on gas lines and drilled for DWV on the North end of Building 'B'.