Subs on Site
<Nutek> (7)
<Warburtons> (9)
<Extreme Fire> (2)
<Extreme Fire> (2)
<Air Doctors> (3)
<Reliance> (6)
<Clegg Steel> (5)
<Red Oak Plumbing> (5)
<DG Concrete> (1)
Work in Progress
(Nutek). Taping East side of 2nd floor Building 'C'. Hung Sheetrock on the 3rd floor of Building 'E'.
(Extreme Fire) Worked on the attic system for Building 'D'
(Air Doctors) Worked on the line sets in Building 'D' Hung the flexible ducts on the last 2 units 3rd floor of Building 'C'
(Reliance) Pulled wire on Building 'E'
(Air Doctors) Worked on the line sets in Building 'D' Hung the flexible ducts on the last 2 units 3rd floor of Building 'C'
(Reliance) Pulled wire on Building 'E'
(Clegg Steel) Installed handrails on the stairs on the Southern tower of Building 'A' and started on the North tower. Installed stair sections in Building 'E' and 'B'
(Red Oak) Worked on gas lines and drilled for DWV on the South end of Building 'B'.
(DG Concrete) Chipped out the concrete around the fire risers in Building 'A' and 'C'.
Sub Meeting 2/11/2013
Rick (Warburtons)
Shawn (Extreme Fire)
Eric (Nutek)
Bryson (Reliance)
Lenny (Air Doctors)
Ether (Red Oak)
Talking Points:
Building ‘A’ final inspection is on 2/27. Reliance will start on electrical trim this week. Bryson (Reliance) would like to talk to the Fire Marshall about closing out Building ‘A’ when he comes by to inspect Building ‘D’ Fire sprinklers. Reliance also needs the fire riser room to be insulated and sheetrocked so that they can set their fire alarm panel. Plumbing trim will be delivered Monday 2/18 and Ether would like to have the building secure by then. I asked Warburtons to clean up the breeze ways in Building ‘A’.
Building ‘C’ gypcrete will be poured on Thursday 2/14 and Friday 2/15. Utek will have 3 framers here tomorrow and said they would have the entire 4th floor drops framed. Lenny(Air Doctors) believes that if they get an early enough start that the flex ducts will be installed by the end of the day as well. Eric (Nutek) said that if they can have the whole floor on Wednesday they will be able to have it all hung by end of the day Thursday.
Building ‘D’ 1st floor hard ducts and line sets should be complete tomorrow. Nutek will have time tomorrow, while waiting for Building ‘C’ 4th floor, to hang the last to units of 2nd floor pre-rock and possibly get started on 3rd floor. Air Doctors will be able to install hard ducts and lines sets in one day per floor. Extreme Fire will have their system tested Tuesday 2/12.
Building ‘E’ 4 way inspection for 1st and 2nd floors in on Wednesday 1/13 and 3rd and 4th floors will be on Monday 1/18. Insulation will also start on Monday 1/18
Building ‘B’ Nutek does not have enough manpower to make the gypcrete schedule and install the pre Rock behind the tubs and cases in Building B. Ether (Red Oak) said that if Nutek will get them the pieces they will hang them.
Schedule:
Building ‘A’
Electrical trim will take an estimated 2 weeks
Plumbing trim (delivery 2/18)
Building ‘C’
1st floor Finish work starts 2/13
1st floor Paint starts 2/18
4th floor drops framed and ducts installed 2/12
4th floor drywall hung 2/14
2nd and 3rd floor gypcrete 2/14
4th floor gypcrete 2/15
Building ‘D’
1st floor hard ducts and line sets Monday 2/11
2nd floor hard ducts and line sets Wednesday 2/13 drops the next day
3rd floor hard ducts and line sets Thursday 2/14 drops the next day
4th floor hard ducts and lines sets Friday 2/15 drops the next day
Building ‘E’
4-way inspection 1st and 2nd floor 2/13
4-way inspection 3rd and 4th floor 2/18
Insulation starts 2/18
Rick (Warburtons)
Shawn (Extreme Fire)
Eric (Nutek)
Bryson (Reliance)
Lenny (Air Doctors)
Ether (Red Oak)
Talking Points:
Building ‘A’ final inspection is on 2/27. Reliance will start on electrical trim this week. Bryson (Reliance) would like to talk to the Fire Marshall about closing out Building ‘A’ when he comes by to inspect Building ‘D’ Fire sprinklers. Reliance also needs the fire riser room to be insulated and sheetrocked so that they can set their fire alarm panel. Plumbing trim will be delivered Monday 2/18 and Ether would like to have the building secure by then. I asked Warburtons to clean up the breeze ways in Building ‘A’.
Building ‘C’ gypcrete will be poured on Thursday 2/14 and Friday 2/15. Utek will have 3 framers here tomorrow and said they would have the entire 4th floor drops framed. Lenny(Air Doctors) believes that if they get an early enough start that the flex ducts will be installed by the end of the day as well. Eric (Nutek) said that if they can have the whole floor on Wednesday they will be able to have it all hung by end of the day Thursday.
Building ‘D’ 1st floor hard ducts and line sets should be complete tomorrow. Nutek will have time tomorrow, while waiting for Building ‘C’ 4th floor, to hang the last to units of 2nd floor pre-rock and possibly get started on 3rd floor. Air Doctors will be able to install hard ducts and lines sets in one day per floor. Extreme Fire will have their system tested Tuesday 2/12.
Building ‘E’ 4 way inspection for 1st and 2nd floors in on Wednesday 1/13 and 3rd and 4th floors will be on Monday 1/18. Insulation will also start on Monday 1/18
Building ‘B’ Nutek does not have enough manpower to make the gypcrete schedule and install the pre Rock behind the tubs and cases in Building B. Ether (Red Oak) said that if Nutek will get them the pieces they will hang them.
Schedule:
Building ‘A’
Electrical trim will take an estimated 2 weeks
Plumbing trim (delivery 2/18)
Building ‘C’
1st floor Finish work starts 2/13
1st floor Paint starts 2/18
4th floor drops framed and ducts installed 2/12
4th floor drywall hung 2/14
2nd and 3rd floor gypcrete 2/14
4th floor gypcrete 2/15
Building ‘D’
1st floor hard ducts and line sets Monday 2/11
2nd floor hard ducts and line sets Wednesday 2/13 drops the next day
3rd floor hard ducts and line sets Thursday 2/14 drops the next day
4th floor hard ducts and lines sets Friday 2/15 drops the next day
Building ‘E’
4-way inspection 1st and 2nd floor 2/13
4-way inspection 3rd and 4th floor 2/18
Insulation starts 2/18