Subs on Site
<SBS> (5)
<Nutek> (10)
<Cardalls> (5)
<Warburtons> (8)
<Air Doctors> (4)
<Warburtons> (8)
<Air Doctors> (4)
<Utek> (2)
<Reliance> (4)
<Red Oak Plumbing> (6)
<Red Oak Concrete> (7)
Work in Progress
Work in Progress
(Nutek) Continued hanging the sheetrock on 2nd floor of Building 'C' and Started taping 2nd floor. Started Pre-rock on 1st floor of Building 'D'
(Warburtons) Worked on the West end Building 'C'. Installed siding on the South center and West sections of Building 'A' as well as the details in the Breezeways on 'A'. Worked on Building 'C' roof. Started drying in Building 'B'.
(Air Doctors) Worked on the hard ducts on the 4th floor in Building 'C' Installed the last 4 unit furnaces on the 2nd floor of Building 'A'/.
(Utek) Framed drops on 3rd floor and will talk to William about starting 4th floor West side drops.
(Reliance) Pulled wire on Building 'E'
(Red Oak) Worked on the DWV and water lines in Building 'E hooked up the gas to the furnaces on 1st floor of Building 'A'. Started gas lines on the South end of Building 'B'.
(Red Oak Concrete) Formed the decks for the East tower of Building 'C' and poured East tower. They told me that they would break it up as well as clean the concrete off the stairs before they left.