Weather: Partly Cloudy 32˚/2˚
Subs on Site
<Nutek> (10)
<Cardalls> (5)
<Warburtons> (8)
<Air Doctors> (4)
<Warburtons> (8)
<Air Doctors> (4)
<Utek> (2)
<Reliance> (4)
<Red Oak Plumbing> (6)
<Red Oak Concrete> (7)
Work in Progress:
Work in Progress:
(Nutek) Continued hanging the sheetrock on 2nd floor of Building 'C' and finished taping 1st floor. Started Pre-rock on 1st floor on Building 'D'.
(Warburtons) Worked on the West end Building 'C'. Installed siding on the South center and West sections of Building 'A' as well as the details in the Breezeways on 'A'. Worked on Building 'C' roof.
(Air Doctors) Worked on the hard ducts on the 4th floor in Building 'C'.
(Utek) Fixed the drops in the center units on the 2nd floor of Building 'C' were they were built too close to the smoke detector.
(Reliance) Orginazed trim on Building 'A'. and started pulling wire on Building 'E'
(Red Oak) Worked on the DWV and water lines in Building 'E hooked up the gas to the furnaces on 1st floor of Building 'A'
(Red Oak Concrete) Formed the decks for the East tower of Building 'C' and poured the West tower. They tore a hole in the plastic to fit the pump truck boom in and the clean out was dumped in front of the breeze way. They told me that they would break it up as well as clean the concrete off the stairs before they left.