Friday 2/1/2013


Weather: Partly Cloudy  35˚/7˚ 

Subs on Site
<Wall to Wall>                  (4)
<SBS>                              (1)
<Nutek>                            (10)
<Cardalls>                        (4)
<Warburtons>                  (8)
<Air Doctors>                   (4)
<Clegg Steel>                  (6)
<Utek>                             (12)
<Reliance>                       (4)
<Red Oak Plumbing>       (6)

Work in Progress:
(Wall to Wall) Cleaned the 8 units on the 4th floor of Building 'A'.

(Nutek) Taped behind the tubs the 4th floor on Building 'E'.  Started hanging the sheetrock on 2nd floor of Building 'C' and continued taping 1st floor.

(SBS) Started on trim and hardware on Building 'A' and hung entry doors on Building 'D'

(Cardalls) Fixed areas from the insulation inspection on Building 'C'.  Finished insulation on Building 'D' 1st floor.

(Warburtons) Worked on the West Breezeway 2nd floor of Building 'C'. Installed siding on the South center and West sections of  Building 'C'.  They cleared snow off of portions of Building 'C's roof so that the run off would not soak the siding guys.

(Air Doctors) Worked on the ducts on the 2nd floor in Building 'C'. Installed flue pipes in Building 'B'.  The sheet rockers are pushing up against them on 2nd floor.

(Clegg Steel) Installed stairs on Building 'C', 'D' and 'E'


(Utek) Finished the gable over builds on Building 'B'.

(Reliance) Set panels on Building 'E' and started trim on Building 'A'.

(Red Oak) Finished and tested gas on 3rd and 4th floors for Building 'E' then started on DWV.   Built the gas lines to hook up the furnaces on Building 'A'.  Started stocking tubs in Building 'B'