Weather: Hazy/Partly Cloudy 32˚/15˚
Subs on Site
<SBS> (2)
<Nutek> (7)
<Warburtons> (9)
<Air Doctors> (3)
<Air Doctors> (3)
<Reliance> (6)
<Red Oak Plumbing> (5)
Work in Progress
(SBS) Installed the extrerior doors on Building 'D' and Building 'C' patio doors. Installed hardware on Building 'A'.
(Nutek). Taping East side of 2nd floor Building 'C'. Hung Sheetrock on the 3rd floor of Building 'E'.
(Nutek). Taping East side of 2nd floor Building 'C'. Hung Sheetrock on the 3rd floor of Building 'E'.
(Air Doctors) Worked on the line sets in Building 'D' Hung the flexible ducts on the last 2 units 3rd floor of Building 'C' and fired up the next 4 furnaces on 1st floor in Building 'A'
(Reliance) Pulled wire on Building 'E'
(Red Oak) Worked on gas lines and drilled for DWV on the South end of Building 'B'.