Weather: Partly Cloudy 28˚/12˚
Subs on Site
<G&M> (2)
<Wall to Wall> (3)
<SBS> (2)
<Nutek> (11)
<Cardalls> (5)
<Warburtons> (11)
<Utek> (2)
<Air Doctors> (2)
<Warburtons> (11)
<Utek> (2)
<Air Doctors> (2)
<Reliance> (5)
<Red Oak Plumbing> (2)
Work in Progress
(G&M) Cut holes for sinks in the last of Building 'A' units.
(Wall to Wall) Striped and cleaned 1st floor Building 'C'.
(SBS) Installed hardware in the North Tower Building 'A'.
(Wall to Wall) Striped and cleaned 1st floor Building 'C'.
(SBS) Installed hardware in the North Tower Building 'A'.
(Nutek) Sanded East side 4th floor of Building 'C'. Hung the drops on one unit in Building 'D'. Textured the paitos in Building 'A'.
(Cardalls) Insulation on 3rd floor Building 'E' and started on 4th floor.
(Utek) Framed drops on Building 'D' 2nd and then 3rd floors.
(Air Doctors) Installed flex ducts on the 2nd floor in Building 'D'. Installed furnaces on the North Tower of Building 'A'.