Friday 2/22/2013


Weather: Partly Cloudy  28˚/12˚ 

Subs on Site
<G&M>                             (2)
<Wall to Wall>                  (3)
<SBS>                              (2)
<Nutek>                            (11)
<Cardalls>                        (5)
<Warburtons>                  (11)
<Utek>                              (2)
<Air Doctors>                   (2)
<Reliance>                       (5)
<Red Oak Plumbing>       (2)


Work in Progress
(G&M) Cut holes for sinks in the last of Building 'A' units.

(Wall to Wall) Striped and cleaned 1st floor Building 'C'.

(SBS) Installed hardware in the North Tower Building 'A'.

(Nutek) Sanded East side 4th floor of Building 'C'.  Hung the drops on one unit in Building 'D'.  Textured the paitos in Building 'A'.

(Cardalls) Insulation on 3rd floor Building 'E' and started on 4th floor.

(Warburtons) Worked on the North side of Building 'C' and the 4th floor West breeze way.

(Utek) Framed drops on Building 'D' 2nd and then 3rd floors.

(Air Doctors) Installed flex ducts on the 2nd floor in Building 'D'.  Installed furnaces on the North Tower of Building 'A'. 

(Reliance) Worked on the North tower trim. Wired the fans and lights in the drops on 2nd floor Building 'D' 

(Red Oak) Installed water lines in Building 'B' and started trim on the South tower Building 'A'