Weather: Partly Cloudy 34˚/16˚
Subs on Site
<G&M> (6)
<Wall to Wall> (3)
<SBS> (3)
<Nutek> (11)
<Cardalls> (7)
<Warburtons> (11)
<Air Doctors> (3)
<Warburtons> (11)
<Air Doctors> (3)
<Reliance> (6)
<Red Oak Plumbing> (6)
Work in Progress
(G&M) Stocked the cabinets in Building 'C'. The painters already had the doors spread in on the 1st floor and did not have enough room for cabinets. G&M stocked the 1st floor cabinets in the garages and labeled them so that my labor can move them into the units tomorrow after the 1st floor is painted.
(Wall to Wall) Primed and Painted first floor Building 'C'.
(SBS) Installed the laundry doors on 2nd floor Building 'C'. Installed hardware on the South tower Building 'A'
(Nutek) Textured West side 4th floor of Building 'C'.
(Cardalls) Insulation on 2nd floor Building 'E' and blew in the insulation on Building 'C'
(Air Doctors) Installed hard ducts on the 3rd floor in Building 'D'. Mario and Curtis had to finish and touch up their fire caulk on 3rd and 4th floors Building 'E'.
(Reliance) Tested out the 4th floor units on the South tower of Building 'A'. Started on the North tower.
(Reliance) Tested out the 4th floor units on the South tower of Building 'A'. Started on the North tower.