Weather: Hazy/Partly Cloudy 29˚/7˚
Subs on Site
<Diamond Z> (4)
<SBS> (2)
<Nutek> (8)
<Warburtons> (9)
<Extreme Fire> (2)
<Extreme Fire> (2)
<Air Doctors> (5)
<Reliance> (6)
<Utek> (3)
<Red Oak Plumbing> (6)
<Knell> (6)
<Knell> (6)
Work in Progress
(Diamond Z) Finished Lathing Building 'D' and started set up for Building 'E'
(SBS) Installed trim in 1st floor Building 'C'. Continued hanging the patio closet doors.
(Nutek). Taped on the East side 3rd floor and 4th floor of Building 'C' and hung the 4 units on the East end 4th floor.
(Extreme Fire) Worked on the attic system for Building 'E'
(Air Doctors) Worked on the rough-in for Building 'B'
(Reliance) Pulled wire on Building 'E'
(Reliance) Pulled wire on Building 'E'
(Utek) Built the drops on 1st floor of Building 'D'
(Red Oak) Worked on gas lines and drilled for DWV on the North end of Building 'B'. Started installing tubs.
(Knell) Poured gypcrete on the West side of Building 'C'