Tuesday 2/12/2013

Weather: Hazy/Partly Cloudy  25˚/4˚ 

Subs on Site
<Diamond Z>                    (4)
<SBS>                              (2)
<Nutek>                            (8)
<Warburtons>                  (9)
<Extreme Fire>                 (2)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Clegg Steel>                   (5)
<Utek>                              (3)
<Red Oak Plumbing>       (3)


Work in Progress
(Diamond Z) Started Lathing Building 'D'

(SBS) Stocked doors and delivered trim for Building 'C'.  Then started hanging the patio closet doors.

(Nutek). Sanded and cleaned the last of the 2nd floor Building 'C' Hung Sheetrock on the 3rd floor of Building 'C' and started hanging 4th floor units.  Fire taped 2 units on 2nd floor Building 'D' 

(Warburtons) worked on the details around Building 'A'. Started roofing Building 'D' Worked on their pump jacks on Building 'C' and in the West Breeze way.

(Extreme Fire) Worked on the attic system for Building 'D'

(Air Doctors) Finished hard ducts on the 1st floor in Building 'D'  Hung the flexible ducts on the units on 4th floor of Building 'C'

(Reliance) Pulled wire on Building 'E' installed the fire alarm panel in Building 'A'

(Clegg Steel) finished installing handrails on the stairs on the Southern and Northern tower of Building 'A'.  Installed stair sections in Building 'E' and 'B'

(Utek) Built the drops on 4th floor of Building 'C'

(Red Oak) Worked on gas lines and drilled for DWV on the North end of Building 'B'.