Subs on Site
<Wholesale Flooring> (7)
<Wall to Wall> (4)
<SBS> (4)
<Diamond Z> (2)
<Nutek> (11)
<Cardalls> (3)
<Extreme Fire> (1)
<Clegg Steel> (7)
<Warburtons> (11)
<Air Doctors> (3)
<Extreme Fire> (1)
<Clegg Steel> (7)
<Warburtons> (11)
<Air Doctors> (3)
<Reliance> (5)
<Red Oak Plumbing> (4)
Work in Progress
(Wholesale Flooring) Installed vinyl on 1st floor of Building 'C' and started tackstrips and pad on 2nd floor of Building 'A'
(Wall to Wall) Primed units on 2nd floor Building 'C'.
(SBS) Trimed in the units on the West side of the 3rd and 4th floors of Building 'C'.
(Wall to Wall) Primed units on 2nd floor Building 'C'.
(SBS) Trimed in the units on the West side of the 3rd and 4th floors of Building 'C'.
(Nutek) Textured the West tower 4th floor of Building 'C'. Hung drywall on the 3rd floor of Building 'D'.
(Cardalls) Finished insulation on 4th floor of Building 'E'.
.
(Clegg Steel) Worked on the stairs for Building 'B'. Installed the deck rails and hand rails on Building 'A'. They set the chimney caps on the roof of Building 'A' but Air Doctors needed to run the vents out before they could set them.
One of the stair sections for Building 'B' was frozen to the ground and when Rob (Clegg Steel) tried to lift it and snapped the knuckle on our lift.
(Warburtons) Worked on the North side of Building 'C' and the 4th floor West breeze way and 3rd floor of the East breezeway..
(Air Doctors) Installed flex ducts on the 3rd floor in Building 'D'. Installed trim on the 4th floor South Tower of Building 'A'. Finished their vent pipes one of the chimney caps.