Subs on Site
<SBS>                              (2)
<Nutek>                            (7)
<Cardalls>                        (5)
<Warburtons>                  (9)
<Air Doctors>                   (3)
<Utek>                             (2)
<Reliance>                       (6)
<Red Oak Plumbing>       (6)
<Red Oak Concrete>       (5)

Work in Progress
(SBS) Installed the extrerior doors on Building 'D' and spread out their hardware on Building 'A'.  Their thresholds are too thin to cover the gypcrete.  We spoke to John (Top Notch) about getting larger ones.

(Nutek) Continued hanging the pre-rock on 2nd floor of Building 'D'. Taping East side of 2nd floor Building 'C'. Started Hanging Sheetrock on the 3rd floor of Building 'E'.

(Cardalls) Finished insulation on Building 'D' 4th floor.and started Behind the tubs and chases in Building 'B'. 

(Warburtons) Worked on the North side Building 'C'. Installed siding on the South center and West sections of  Building 'A' as well as the details in the Breezeways on 'A'.  Dried in Building 'B'. and started Building 'D' roof.

(Air Doctors) Worked on the hard ducts on the 4th floor in Building 'C'  Hung the flexible ducts on 3rd floor of Building 'C' and fired up the first 4 furnaces on 1st floor in Building 'A'

(Utek) Framed the last 2 unit drops on 3rd floor 

(Reliance) Pulled wire on Building 'E'

(Red Oak) Worked on gas lines on the South end of Building 'B'.  Passed DWV inspection for Building 'E'.

(Red Oak Concrete) Cleaned the concrete off the whole of Building 'B' and washed the windows with at sponge..