Weather: Partly Cloudy 27˚/8˚
Subs on Site
<Wall to Wall> (2)
<Diamond Z> (4)
<SBS> (2)
<Nutek> (11)
<Cardalls> (5)
<Warburtons> (9)
<Extreme Fire> (2)
<Warburtons> (9)
<Extreme Fire> (2)
<Air Doctors> (3)
<Reliance> (6)
<Red Oak Plumbing> (6)
Work in Progress
(Wall to Wall) Prepped 4 units on the 1st floor Building 'C'.
(Diamond Z) Finished Lathing Building 'E'
(Diamond Z) Finished Lathing Building 'E'
(SBS) Installed trim in 2nd floor Building 'C'. The laundry doors were not on site and were not installed. John (Top Notch) said the would be on site tomorrow morning so that Ryan could install them before Wall to Wall painted.
(Nutek). Taped on the West side 3rd floor and 4th floor of Building 'C'. Hung the pre Rock and lid on 4th floor Building 'D' Hung the last of the drywall behind the tubs on Building 'B'.
(Cardalls) Started insulating 1st floor Building 'E'
(Extreme Fire) Cut the sprinkler heads for Building 'D' 1st floor and worked on the details in Building 'A'
(Air Doctors) Worked hard ducts on the 2nd floor in Building 'D' Hung the flexible ducts on the 1st floor of Building 'D'.
(Reliance) Installed trim on the West tower of Building 'A'.
(Reliance) Installed trim on the West tower of Building 'A'.
(Red Oak) Installed tubs and DWV in Building 'B'.
Sub Meeting 2/11/2013
Rick (Warburtons)
Doug (Cardalls)
Eric (Nutek)
Bryson (Reliance)
William (Air Doctors)
Ether (Red Oak)
Rob (Wall to Wall)
Talking Points:
I asked everyone to clean up their work area and even just a little more so that the sight does not look like a dump.
Building ‘A’ final inspection is on 2/27. Reliance will have the South tower 1st - 4th floors will be trimmed out today. Reliance will have the remainder Building ‘A’ units complete this week, they will need a couple days next week to install the light poles and corridor lights and signs. The block-outs for the lights in corridors are correct but the exit sign blocks need to be fixed. Rick (Warburtons) told Bryson to let Jose (Warburtons) know and they would get them fixed. Plumbing trim will be delivered Tuesday 2/19 and Ether thought they would need through the weekend to trim the South tower. He would also would like to have the building secure. I asked Ether (Red Oak) to get the furnaces on the South end of 2nd floor Building ‘A’ hooked to the gas so that we can use the heaters.
Building ‘C’ The laundry room doors are not on site. John (Top Notch) said they will be delivered tomorrow morning. Ryan (SBS) said that if they are here by noon 1st and 2nd floors will be hung by the end of the day. Rob (Wall to Wall) said that will work so that they do not have to come back to prime. Ether asked to put water heaters in the units in box Rob (Wall to Wall) said that would not be a problem.
Building ‘D’ gypcrete will be poured on Thursday 2/28. Fire caulk inspection will be tomorrow morning for 1st and 2nd floors. The framers will be here on Wednesday and will frame the drops at a rate of ½ day per floor. Air Doctors will be able to stay ahead of them. Nutek will be able to hang one floor per day.
Building ‘E’ 4 way inspection for 3rd and 4th floors will be on Tuesday 1/19 because today is a holiday. Insulation on 1st floor will be complete by the end of the day Tuesday 1/19 so that Nutek can hang the pre rock.
Building ‘B’ Nutek finished pre Rock behind the tubs and cases in Building B today and will tape them tomorrow.. Ether (Red Oak) hung some of the units this weekend so that they could continue setting the tubs. They will be ready for DWV on Thursday 2/21.
Schedule:
Building ‘A’
Carpet West tower 2/25
1st floor Paint started 2/18
1st floor and 4 units on 2nd floor Vinyl 2/25
2nd floor finish work complete 2/19
West side 3rd floor Texture complete by 10 am 2/20
East side 4th floor Texture complete end of day 2/20
Building ‘D’
1st floor drywall hung 2/20
2nd floor hard ducts and line sets Tuesday 2/19 drops the next day.
3rd floor hard ducts and line sets Wednesday 2/20 drops the next day.
4th floor hard ducts and lines sets Thursday 2/21 drops the next day.
Building ‘E’
4-way inspection 3rd and 4th floor 2/18
Insulation starts 2/18 1st floor.
Pre Rock on 1st floor starts Wednesday 2/20
Rick (Warburtons)
Doug (Cardalls)
Eric (Nutek)
Bryson (Reliance)
William (Air Doctors)
Ether (Red Oak)
Rob (Wall to Wall)
Talking Points:
I asked everyone to clean up their work area and even just a little more so that the sight does not look like a dump.
Building ‘A’ final inspection is on 2/27. Reliance will have the South tower 1st - 4th floors will be trimmed out today. Reliance will have the remainder Building ‘A’ units complete this week, they will need a couple days next week to install the light poles and corridor lights and signs. The block-outs for the lights in corridors are correct but the exit sign blocks need to be fixed. Rick (Warburtons) told Bryson to let Jose (Warburtons) know and they would get them fixed. Plumbing trim will be delivered Tuesday 2/19 and Ether thought they would need through the weekend to trim the South tower. He would also would like to have the building secure. I asked Ether (Red Oak) to get the furnaces on the South end of 2nd floor Building ‘A’ hooked to the gas so that we can use the heaters.
Building ‘C’ The laundry room doors are not on site. John (Top Notch) said they will be delivered tomorrow morning. Ryan (SBS) said that if they are here by noon 1st and 2nd floors will be hung by the end of the day. Rob (Wall to Wall) said that will work so that they do not have to come back to prime. Ether asked to put water heaters in the units in box Rob (Wall to Wall) said that would not be a problem.
Building ‘D’ gypcrete will be poured on Thursday 2/28. Fire caulk inspection will be tomorrow morning for 1st and 2nd floors. The framers will be here on Wednesday and will frame the drops at a rate of ½ day per floor. Air Doctors will be able to stay ahead of them. Nutek will be able to hang one floor per day.
Building ‘E’ 4 way inspection for 3rd and 4th floors will be on Tuesday 1/19 because today is a holiday. Insulation on 1st floor will be complete by the end of the day Tuesday 1/19 so that Nutek can hang the pre rock.
Building ‘B’ Nutek finished pre Rock behind the tubs and cases in Building B today and will tape them tomorrow.. Ether (Red Oak) hung some of the units this weekend so that they could continue setting the tubs. They will be ready for DWV on Thursday 2/21.
Schedule:
Building ‘A’
Carpet West tower 2/25
Final inspection 2/27
Building ‘C’1st floor Paint started 2/18
1st floor and 4 units on 2nd floor Vinyl 2/25
2nd floor finish work complete 2/19
West side 3rd floor Texture complete by 10 am 2/20
East side 4th floor Texture complete end of day 2/20
Building ‘D’
1st floor drywall hung 2/20
2nd floor hard ducts and line sets Tuesday 2/19 drops the next day.
3rd floor hard ducts and line sets Wednesday 2/20 drops the next day.
4th floor hard ducts and lines sets Thursday 2/21 drops the next day.
Building ‘E’
4-way inspection 3rd and 4th floor 2/18
Insulation starts 2/18 1st floor.
Pre Rock on 1st floor starts Wednesday 2/20