Wednesday 2/27/2013

Weather: Sunny  28˚/4˚ 

Subs on Site
<Wholesale Flooring>      (7)
<Wall to Wall>                  (4)
<SBS>                              (4)
<Diamond Z>                    (2)
<Nutek>                            (11)
<Cardalls>                        (3)
<Extreme Fire>                 (1)
<Clegg Steel>                   (7)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (5)
<Red Oak Plumbing>       (4)


Work in Progress
(Wholesale Flooring) Installed carpet on the 2nd floor of Building 'A' and tack strip and pad on 3rd floor.

(Wall to Wall) Painted units on 2nd floor Building 'C'.

(SBS) Trimed in the units on the West side of the 4th floor of Building 'C' and worked on hardware in Building 'A'.

(Diamond Z) Started laying stone on South West side of Building 'E'.

(Nutek) Textured the West tower 4th floor of Building 'C'.  Hung drywall on the 3rd floor of Building 'D'.

(Cardalls) Insulated the fire riser rooms in 'C', 'D', and 'E' and installed baffles on the patios in Building 'C' and 'D'

(Extreme Fire) pumped the pressure on the fire sprinklers on Building 'A' to 200 lbs.  We checked each unit while the system filled.  The stocked the pipe for and worked on Building 'B's attic system.   
.
(Clegg Steel) Worked on the stairs for Building 'B'.  Installed the deck rails and hand rails on Building 'A'.


(Warburtons) Worked on the North side of Building 'C' and the 4th floor East breezeway..

(Air Doctors) Installed flex ducts on the 4th floor in Building 'D'.  Installed trim on the North Tower of Building 'A'.  Finished their vent pipes one of the chimney caps. 

(Reliance) Worked on the last 4 units North tower trim. Wired the fans and lights in the drops on 4th floor Building 'D' 

(Red Oak) Installed trim on the South tower Building 'A'