Tuesday 2/19/2013


Weather: Partly Cloudy  31˚/17˚ 

Subs on Site
<Wall to Wall>                  (3)
<Diamond Z>                    (4)
<SBS>                              (3)
<Nutek>                            (11)
<Cardalls>                        (7)
<Warburtons>                  (9)
<Extreme Fire>                 (1)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Red Oak Plumbing>       (6)


Work in Progress
(Wall to Wall) Prepped first floor and 1/2 of 2nd floor Building 'C'.

(Diamond Z) Passed lath inspection and scratched Building 'E'

(SBS) Installed the laundry doors on 1st floor.  Installed hardware on the South tower Building 'A'

(Nutek). Textured West side 3rd floor of Building 'C'.  Taped the pre Rock and lid on 4th floor Building 'D'.  Taped the last of the drywall behind the tubs on Building 'B'.

(Cardalls) Finished insulation on 1st floor Building 'E' and blew in the insulation on Building 'C'

(Warburtons)  Worked on their pump jacks on Building 'C' finishing both ends up to the soffit and in the West Breeze way and patios up to 4th floor..

(Extreme Fire) Cut the sprinkler heads for Building 'D' 2nd floor and worked on the details in Building 'A'

(Air Doctors) Installed flex ducts on 1st floor and worked hard ducts on the 3rd floor in Building 'D'.  Finished fire caulk on 3rd and 4th floors Building 'E', inspection moved to Wednesday.  

(Reliance) Installed trim on the West tower of Building 'A'.  The inspector noted that the panels did not have GFCI breaker for our temp outlet.  Jared said he could switch them out.

(Red Oak) Installed tubs and DWV in Building 'B'.  They also had the trim for Building 'A' delivered..