Weather: Sunny 88˚/60˚
Subs on Site
<Questar> (3)
<TouchStone> (10)
<Reliance> (2)
<Red Oak> (9)
<DG Concrete> (4)
Work in Progress:
(Questar) ran their main line from Main Street North to the club house and started up the main road. They have to go under the parking because the need 8' set back from the building and do not want to be under the sidewalk.
(TouchStone) framed interior walls and rolled the floor on the South End of Building 'A'.
(Reliance) Ran temp power to Building 'A'
(Red Oak)Finished forming the foundation walls for Building 'A' garage and passed inspection, continued forming Building 'D' foundation walls.
(DG Concrete) Backfilled Building 'C' and dug a trench to their trailers for an upgraded power line because their A/C units were popping the breakers.
Sub Meeting:
(DG Concrete)Curb and gutter is still on schedule. (TouchStone) would like to have the irrigation meter in front of Building 'D' set ASAP so they can have temp water for their trailers.
(Red Oak) will be pouring Building 'A' Garage walls and the first half of Building 'D' walls on Wednesday, Try for a Thursday pour on the 2nd half. Then finish the breeze ways on Friday.