Monday 4/29/2013

Weather: Partly Cloudy and windy 80˚/30˚ 

Subs on Site
<Elite Structures>             (2)
<Huskies>                        (5)
<Nutek> 
                           (9)
<Wall to Wall>                  (3)
<SBS>                              (2)
<Diamond Z>                    (3)
<Warburtons>                  (10)
<Reliance>                       (2)
<Air Doctors>                    (3)
<DG Concrete>                 (3)

Work in Progress
(Elite Structures) Drilled the footings for Building 'A' parking structures and passed inspection.

(Huskies) Laid the irrigation pipes around Building 'A'. 

(Wall to Wall) Prepped 2nd and 3rd floor on the South Tower of Building 'B'.  Rob noticed that some of the trim pieces on Building 'A' siding had hammer marks.  I asked Jose (Warburtons) to walk through and check and replace trims.

(SBS) Installed trim on the 4th floor of the South end of Building 'B'..

(Nutek)  Taped on 2nd, 3rd, & 4th South floor Building 'B'.  Taped patios and breezeways in Building 'E'&'B'
.
(Diamond Z) Continued the stone on the East Columns and East side of Building 'B'. And stoned around the window wells on Buildings 'C' and 'D'.

(Warburtons) Worked on the South side soffit of Building 'D" entry.  Worked on the patios and breezeway and the South end of Building 'B'.  The siding on the breezeways in the South end of Building 'B' was wavy.  The framing is not strait.  I call Alma (Utek) and he will try to make it down Saturday to straiten them out.

(Reliance) Wired on the Club House.

(Air Doctors) Installed vents in the Club House.

(DG Concrete) Backfilled around Building 'D' and built the rock walls.




Sub Meeting 4/29/2013


Rob (Wall to Wall)
Chris (Nutek)
EJ (Air Doctors)
Jared (Reliance)

Talking Points:
Clean-up: Clean your trash and organize your materials.
1st floor Stairs will be poured on Thursday 5/2 in all Buildings.
Building ‘C’  I ask EJ to check the condenser pad area on North Side of the Building because it is tight for space.  Concrete sidewalks poured on Friday 5/3.
Building ‘D’  Siding complete 4/30.  Carpet install starts 5/6
Building ‘E’   Appliances delivered 4/30. Siding complete 5/7.
Building ‘B’  Finish work on the South end of 4th floor will be complete today 4/29,  Paint on the  South Tower complete 5/3.  North Tower texture: 2nd floor today, 3rd floor Wednesday 5/1, 4th floor Friday 5/3 Complete by 5/3.  
Club House No attic access framed.  Reliance will fur the pony wall behind the cabinets up for their plugs.  4 way is on 5/1.  Insulation starts 5/6
 
Schedule:
Building ‘C’
Condensers set 5/1-5/3
Stairs poured Thursday 5/2
Sidewalks poured Friday 5/3
Building ‘D’
Siding complete 4/30
Carpet install 5/6
Building ‘E’
Appliances delivered 4/30
Siding complete 5/7
Building ‘B’
Paint South tower  4/30 - 5/3.
Texture 3rd and 4th North tower complete 5/3.
Paint North tower 5/6 -5/10
Cabinets delivered 5/13.
Club House
4-way inspection 5/1
Insulation 5/6




Friday 4/26/2013

Weather: Partly Cloudy 57˚/30˚ 

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (1)
<SBS>                              (3)
<Nutek>                            (9)
<Diamond Z>                    (3)
<Warburtons>                  (8)
<Reliance>                       (3)
<Red Oak>                       (3)

Work in Progress
(Huskies) Dug trenches for the irrigation pipes around Building 'A'. 

(Wall to Wall) Painted 1st floor Building 'B'.  Caulked and filled the South breezeway of Building 'A'. 

(SBS)  Finished Installing trim in the South end of Building 'B' 3rd floor..

(Nutek)  Textured on 3rd, & 4th South floor Building 'B'.  Taped patios and breezeways in Building 'C'&"D'
.
(Diamond Z) Continued the stone on the East Columns and East side of Building 'B'.

(Warburtons) Worked on the West side of Building 'D" entry.  Worked on the patios and breezeway and the South end of Building 'B'.





Thursday 4/25/2013

Weather: Partly Cloudy 57˚/30˚ 

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (3)
<SBS>                              (3)
<Nutek>                            (9)
<Diamond Z>                    (3)
<Warburtons>                  (10)
<Reliance>                       (3)
<DG Concrete>                 (3)

Work in Progress
(Huskies) Dug trenches for the irrigation pipes around Building 'A'.  I spoke with Salvador about the s 

(Wall to Wall) Painted 1st floor Building 'B'.  Caulked and filled the South breezeway of Building 'A'. 

(SBS) Installed blinds and mirrors in Building 'A's rented units.  Finished Installing trim in the South end of Building 'B' 2nd floor..

(Nutek)  Textured on 3rd, & 4th South floor Building 'B'.  Taped patios and breezeways in Building 'C'&"D'
.

(Diamond Z) Continued the stone on the East Columns and East side of Building 'B'.

(Warburtons) Worked on the North side of Building 'D" entry.  Worked on the patios and breezeway and the South end of Building 'B'.  Finished siding on the Club House.


(Reliance) Trim on Building 'E'.

(DG Concrete) Fixed the sidewalks around 'C' and the condenser pads..





Wednesday 4/24/2013

Weather: Partly Cloudy 57˚/30˚ 

Subs on Site
<Huskies>                        (4)
<G&M Woods>                 (4)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Nutek>                            (11)
<Diamond Z>                    (3)
<Warburtons>                  (10)
<Reliance>                       (5)
<Clegg Steel>                   (5)
<DG Concrete>                 (3)
<Elite Structures>            (2)

Work in Progress
(Huskies) Dug trenches for the irrigation pipes around Building 'A'. Found the sleeves under the pavement. 

(G&M Woods) Installed cabinets on 4th floor in Building 'E'.

(Wall to Wall) Prepped and primed the North end of 1st floor Building 'B'.

(SBS) Installed blinds and mirrors in Building 'A's rented units.  Finished Installing trim in the South end of Building 'B' 2nd floor..

(Nutek)  Taped on 2nd, 3rd, & 4th floor Building 'B'.  Taped patios and breezeways in Building 'A'.

(Diamond Z) Continued the stone on the East Columns and East side of Building 'B'.

(Warburtons) Worked on the South side of Building 'D" entry.  Worked on the patios and breezeway and the South end of Building 'B'.  Siding on the Club House.


(Reliance) Trim on Building 'E'.

(Clegg Steel) Installed the handrails on the stairs and the chimney caps.

(DG Concrete) Backfilled Building 'D' and built the rock walls around it.

(Elite Structures) Cut the asphalt were their footing will be poured.





Tuesday 4/23/2013


Weather: Partly Cloudy 49˚/30˚ 

Subs on Site
<Huskies>                        (4)
<G&M Woods>                 (4)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Nutek>                            (11)
<Diamond Z>                    (3)
<Warburtons>                  (10)
<Reliance>                       (5)

Work in Progress
(Huskies) Dug trenches for the irrigation pipes around Building 'A'.  Dug crossing under the road base were the sidewalks are prepped in front of Building 'C' and 'D'.

(G&M Woods) Installed cabinets on 4th floor in Building 'E'.

(Wall to Wall) Prepped and primed the South end of 1st floor Building 'B'.

(SBS) Installed blinds and mirrors in Building 'A's rented units. Installed trim in the South end of Building 'B' 2nd floor..

(Nutek)  Taped on 2nd, 3rd, & 4th floor Building 'B'.  Taped patios and breezeways in Building 'C'.

(Diamond Z) Continued the stone on the East Columns and South end of Building 'B'.

(Warburtons) Worked on the South side of Building 'D" entry.  Worked on the patios and breezeway and the South end of Building 'B'.  Started siding on the East side of the Club House.


(Reliance) Trim on Building 'E'. 





Monday 4/22/2013


Weather: Partly Cloudy 60˚/30˚ 

Subs on Site
<G&M Woods>                 (4)
<Wall to Wall>                  (3)
<SBS>                              (2)
<Nutek>                            (11)
<Diamond Z>                    (3)
<Warburtons>                  (10)
<Reliance>                       (5)
<DG Concrete>                (3)

Work in Progress
(G&M Woods) Installed cabinets in Building 'E'.

(Wall to Wall) Started prepping and primed the North end of 1st floor Building 'B'.

(SBS) Pick-up base in Building 'D'.  Installed door frames on the Club House.  Installed blinds in Building 'A's rented units..

(Nutek)  Taped on 2nd, 3rd, & 4th floor Building 'B'.  Hung the patios and breezeways in Building 'B'.

(Diamond Z) Continued the stone on the East Columns and South end of Building 'B'.

(Warburtons) Finished Building 'C'.  Worked on the patios and breezeway on the North end of Building 'B'.
(Reliance) Trim on Building 'E'. 

(DG Concrete) Re-dug the meter on the West end of on Building 'E' which was only 3 feet deep on the building side causing the setter to be crooked.  Dusty (Maeser) came and Vacuumed the 2' meter cans to replace them with 30" ones for Building 'C' 



.

Sub Meeting 4/22/2013

Rick (Warburtons)
Rob (Wall to Wall)
Chris (Nutek)
Jesse (Diamond Z)
Zac (Huskies Landscaping)

Talking Points:
Clean-up: Clean your trash and organize your materials.
Building ‘C’  Handrails and chimney caps Thursday 4/19.  
Building ‘D’  Siding complete 4/29.
Building ‘E’   Cabinets install complete 4/25.   Electrical trim complete 4/25.  Rob (Wall to Wall) walked Building ‘E’ with Rick (Warburtons) to show him the hammer marks on the door trim.
Building ‘B’  Drywall, tape, and texture on the South end of 2nd floor will be complete today 4/22,  The remainder of  South Tower 4/26.  North Tower Complete by 5/3.  Chris (Nutek) is going to try to get more tapers on site to finish earlier.  Finish work on the 2nd floor North Tower will start tomorrow 4/23.  Paint on the 1st floor will be painted by Thursday 4/25.
Club House Siding is to start today Monday 4/22.  Rick (Warburtons) asked Jesse (Diamond Z) to mark the heights for the stone.
Landscaping Zac estimates 2 weeks per building.  They need to coordinate with Shad (DG Concrete) for installation of sleeves under the sidewalks.
 
Schedule:
Building ‘C’
Siding Complete today 4/22
Chimney Caps and stair rails 4/23.
Building ‘D’
Plumbing gas lines starts 4/23.
Building ‘E’
Cabinets installed  4/25.
Electrical trim complete 4/25.
Building ‘B’
Texture 2nd floor South complete 4/22.
Finish work Starts 2nd floor South 4/23.
Paint 1st floor  4/22 - 4/25.
Texture 3rd and 4th South tower complete 4/25.




Friday 4/19/2013


Weather: Partly Cloudy 50˚/22˚ 

Subs on Site
<G&M Woods>                 (4)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Knell>                             (6)
<Nutek>                            (11)
<Diamond Z>                    (3)
<Air Doctors>                    (7)
<Warburtons>                   (8)
<Reliance>                       (5)

Work in Progress
(G&M Woods) Installed cabinets in Building 'E'.  I asked Geary to check for damaged cabinets in Building 'C'.

(Wall to Wall) Touch up in Building 'C' South Tower.

(Knell) Installed gypcrete on the North Tower of Building 'B'.

(SBS) Started trim on the South end of 1st Floor.

(Nutek)  Taped on 2nd, 3rd, & 4th floor Building 'B'.

(Diamond Z) Continued the stone South end of Building 'B'.

(Air Doctors) Stocked Furnaces in Building 'E' and worked on 3 of the furnaces in Building 'C' that had something wrong with them.  They had to cut holes in units on the 2nd and 4th floors of Building 'C'.

(Warburtons) Worked on the breezeway and patios on the North end of Building 'B'.  They also started on the exterior of Building 'B'.  Jose started working on the upper portions of Building 'C' with the lift.

(Reliance) Trim on Building 'E'.  Installed the fire panel in Building 'E' and 'B'.


Thursday 4/18/2013

Weather: Light Snow 45˚/26˚ 

Subs on Site
<G&M Woods>                 (4)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Knell>                             (6)
<Nutek>                            (11)
<Diamond Z>                    (3)
<Air Doctors>                    (7)
<Warburtons>                  (8)
<Reliance>                       (5)
<Red Oak>                       (3)
<DG Concrete>                (3)

Work in Progress
(G&M Woods) Started to install cabinets in Building 'E'.

(Wall to Wall) Touch up in Building 'C' South Tower.

(Knell) Installed gypcrete on the South Tower of Building 'B'.

(SBS) Finished trim on the North end of 1st Floor.

(Nutek)  Taped on 2nd, 3rd, & 4th floor Building 'B'. Cleaned and moved extra drywall from North Tower of Building 'B'.  We found some Touch-up in Building 'C' that they missed.

(Diamond Z) Continued the stone on the East Columns and South end of Building 'B'.

(Air Doctors) Stocked Furnaces in Building 'E' and worked on 3 of the furnaces in Building 'C' that had something wrong  with them.

(Reliance) Trim on Building 'E'.  Installed the fire panel in Building 'E' and 'B'.

(Red Oak) Stocked their water heaters into Building 'E'.

(DG Concrete) Built rock walls on Building 'D'.

Mario and Curtis installed the window wells on Building 'D'.