Work in Progress
(Elite Structures) Drilled the footings for Building 'A' parking structures and passed inspection.
(Wall to Wall) Prepped 2nd and 3rd floor on the South Tower of Building 'B'. Rob noticed that some of the trim pieces on Building 'A' siding had hammer marks. I asked Jose (Warburtons) to walk through and check and replace trims.
(SBS) Installed trim on the 4th floor of the South end of Building 'B'..
(Nutek) Taped on 2nd, 3rd, & 4th South floor Building 'B'. Taped patios and breezeways in Building 'E'&'B'
.
.
(Diamond Z) Continued the stone on the East Columns and East side of Building 'B'. And stoned around the window wells on Buildings 'C' and 'D'.
(Warburtons) Worked on the South side soffit of Building 'D" entry. Worked on the patios and breezeway and the South end of Building 'B'. The siding on the breezeways in the South end of Building 'B' was wavy. The framing is not strait. I call Alma (Utek) and he will try to make it down Saturday to straiten them out.
(Reliance) Wired on the Club House.
(Air Doctors) Installed vents in the Club House.
Sub Meeting 4/29/2013
Rob (Wall to Wall)
Chris (Nutek)
EJ (Air Doctors)
Jared (Reliance)
Talking Points:
Clean-up: Clean your trash and organize your materials.
1st floor Stairs will be poured on Thursday 5/2 in all Buildings.
Building ‘C’ I ask EJ to check the condenser pad area on North Side of the Building because it is tight for space. Concrete sidewalks poured on Friday 5/3.
Building ‘D’ Siding complete 4/30. Carpet install starts 5/6
Building ‘E’ Appliances delivered 4/30. Siding complete 5/7.
Building ‘B’ Finish work on the South end of 4th floor will be complete today 4/29, Paint on the South Tower complete 5/3. North Tower texture: 2nd floor today, 3rd floor Wednesday 5/1, 4th floor Friday 5/3 Complete by 5/3.
Club House No attic access framed. Reliance will fur the pony wall behind the cabinets up for their plugs. 4 way is on 5/1. Insulation starts 5/6
Schedule:
Building ‘C’
Condensers set 5/1-5/3
Stairs poured Thursday 5/2
Sidewalks poured Friday 5/3
Building ‘D’
Siding complete 4/30
Carpet install 5/6
Building ‘E’
Appliances delivered 4/30
Siding complete 5/7
Building ‘B’
Paint South tower 4/30 - 5/3.
Texture 3rd and 4th North tower complete 5/3.
Paint North tower 5/6 -5/10
Cabinets delivered 5/13.
Club House
4-way inspection 5/1
Insulation 5/6