Thursday 4/4/2013


Weather: Light Clouds 67˚/42˚ 

Subs on Site
<Wholesale Flooring>      (8)
<Sterns>                          (6)
<Wall to Wall>                  (1)
<SBS>                              (3)
<Nutek>                            (6)
<Warburtons>                  (8)
<Air Doctors>                   (3)
<Reliance>                       (3)
<Utek>                              (3)

Work in Progress
(Wholesale Flooring) Installed carpet in Building 'C'.

(Sterns) Poured the side walks on the East side of Building 'A'.

(Wall to Wall) Painted the inside of the door frames on Building 'E'.

(SBS) Installed trim on 3rd floor of Building 'E' and hardware in Building 'C'.

(Nutek) Taped the fourth floor patios in Building 'A' & 'C'.  

(Warburtons) Siding in the corridors of Building 'B'.  And the entry gables on the North side of Building 'D'.

(Air Doctors) Trim for Building 'C'.  Finished the hard ducts for the North Tower Building 'B' and installed the flex ducts on 2nd, 3rd, and 4th floor on the South tower of Building 'B'.

(Reliance) Worked on the corridors of Building 'C'.  

(Utek) Framed the drops on 3rd and 4th floors on North tower in Building 'B'.