Weather: Partly Cloudy 47˚/32˚
Subs on Site
<Sterns> (6)
<Wall to Wall> (3)
<Wall to Wall> (3)
<SBS> (3)
<Nutek> (9)
<Nutek> (9)
<Warburtons> (8)
<Reliance> (3)
<Reliance> (3)
<Utek> (1)
<Red Oak> (6)
<DG Concrete> (3)
<Red Oak> (6)
<DG Concrete> (3)
Work in Progress
(Sterns) Re-poured the stairs on the South East side of Building 'A'.
(Wall to Wall) Painted 1st and 2nd floor Building 'E'.
(SBS) Installed hardware in Building 'C'.
(Wall to Wall) Painted 1st and 2nd floor Building 'E'.
(SBS) Installed hardware in Building 'C'.
(Nutek) Taped the 1st floor and corridors of Building 'B'. Hung units on the South Tower of Building 'B'.
(Warburtons) Siding in the patios of Building 'E'. Siding on the entry on the North West of Building 'C'. Cleaned around the Buildings..
(Reliance) Worked on the trim on Building 'D'.
(Utek) Framed the entry gable, pony wall, and furred out the walls on the Club House.
(Red Oak) Installed the water proofing on Building 'B' corridors and patios.
(DG Concrete) Finished working on the details around Building 'A'. Back-filled around Building 'E' and started rock walls in front of Building 'C'
Warburtons was lifting siding up to the 4th floor on Building 'E' and the lift's tire blew out.
We installed the mailboxes for the site. Building 'A' will face the asphalt until the ADA ramp is poured.
Warburtons was lifting siding up to the 4th floor on Building 'E' and the lift's tire blew out.
We installed the mailboxes for the site. Building 'A' will face the asphalt until the ADA ramp is poured.