Subs on Site
< Precision Asphalt> (2)
<Green Clean> (2)
<Wall to Wall> (3)
<Nutek> (9)
<Diamond Z> (3)
<Air Doctors> (3)
<Clegg Steel> (3)
<Warburtons> (8)
<Reliance> (3)
<Air Doctors> (3)
<Clegg Steel> (3)
<Warburtons> (8)
<Reliance> (3)
<Red Oak> (6)
Work in Progress
(Precision Asphalt) Installed signs on the posts that Big Dave (Deputy Fire Marshall) did not shake during his inspection yesterday while the concrete was still wet. They installed the ADA sign as well.
(Green Clean) Started on the windows and window frames in Building 'D'.
(Wall to Wall) Prepped and Primed 4th floor Building 'E'.
(Nutek) Taped the 1st floor and corridors of Building 'B'. Started Taping 2nd floor Building 'B'. Hung the lid on 4th floor North Tower of Building 'B'.
(Diamond Z) Installed the stone on the East Columns. of Building 'B' and Started on the South End.
(Air Doctors) Ran the flues for the water heaters and furnaces on Building 'C'.
(Clegg Steel) Re installed the guardrails and grab bars on the South end of Building 'A'.
(Warburtons) Siding in the corridors of Building 'D'. Siding on the entry on the North West of Building 'C'. Cleaned around the Buildings..
(Reliance) Started on the trim on Building 'E'.
(Red Oak) Poured Building 'B' South corridors and patios. I asked them that when they finish the pour they tuck the waterproofing under the house wrap. (See Picture below)