Tuesday 4/23/2013


Weather: Partly Cloudy 49˚/30˚ 

Subs on Site
<Huskies>                        (4)
<G&M Woods>                 (4)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Nutek>                            (11)
<Diamond Z>                    (3)
<Warburtons>                  (10)
<Reliance>                       (5)

Work in Progress
(Huskies) Dug trenches for the irrigation pipes around Building 'A'.  Dug crossing under the road base were the sidewalks are prepped in front of Building 'C' and 'D'.

(G&M Woods) Installed cabinets on 4th floor in Building 'E'.

(Wall to Wall) Prepped and primed the South end of 1st floor Building 'B'.

(SBS) Installed blinds and mirrors in Building 'A's rented units. Installed trim in the South end of Building 'B' 2nd floor..

(Nutek)  Taped on 2nd, 3rd, & 4th floor Building 'B'.  Taped patios and breezeways in Building 'C'.

(Diamond Z) Continued the stone on the East Columns and South end of Building 'B'.

(Warburtons) Worked on the South side of Building 'D" entry.  Worked on the patios and breezeway and the South end of Building 'B'.  Started siding on the East side of the Club House.


(Reliance) Trim on Building 'E'.