Subs on Site
<G&M Woods> (4)
<Wall to Wall> (3)
<SBS> (4)
<Wall to Wall> (3)
<SBS> (4)
<Knell> (6)
<Nutek> (11)
<Nutek> (11)
<Diamond Z> (3)
<Air Doctors> (7)
<Warburtons> (8)
<Reliance> (5)
<Red Oak> (3)
<DG Concrete> (3)
<DG Concrete> (3)
Work in Progress
(G&M Woods) Started to install cabinets in Building 'E'.
(Wall to Wall) Touch up in Building 'C' South Tower.
(Wall to Wall) Touch up in Building 'C' South Tower.
(Knell) Installed gypcrete on the South Tower of Building 'B'.
(SBS) Finished trim on the North end of 1st Floor.
(Nutek) Taped on 2nd, 3rd, & 4th floor Building 'B'. Cleaned and moved extra drywall from North Tower of Building 'B'. We found some Touch-up in Building 'C' that they missed.
(Diamond Z) Continued the stone on the East Columns and South end of Building 'B'.
(Air Doctors) Stocked Furnaces in Building 'E' and worked on 3 of the furnaces in Building 'C' that had something wrong with them.
(Reliance) Trim on Building 'E'. Installed the fire panel in Building 'E' and 'B'.