Wednesday 4/3/2013

Weather: Partly Cloudy 63˚/37˚ 

Subs on Site
<Wholesale Flooring>      (8)
<Sterns>                          (6)
<Wall to Wall>                  (1)
<SBS>                              (3)
<Nutek>                            (6)
<Cardalls>                        (2)
<Warburtons>                  (8)   
<Air Doctors>                   (3)
<Reliance>                       (3)
<Utek>                              (3)
<Precision Asphalt >        (2)

Work in Progress
(Wholesale Flooring) Installed vinyl on 2nd,3rd, and 4th floors in Building 'D' and started carpet on 'C'

(Sterns) Saw cut the corridors in Building 'E'.  Formed the side walks on the East side of Building 'A'.

(Wall to Wall) Painted the inside of the door frames on Building 'C' and 'D'.

(SBS) Installed trim on 3rd floor of Building 'E' and hardware in Building 'C'.

(Nutek) Taped the corridors in Building 'A' & 'C'.  Pre rocked the 4th floor North Tower in Building 'B'.  Fire taped the whole of the North Tower.

(Cardalls) Blew in Building 'E' attic and delivered the stickers for the power panels.

(Warburtons) Siding in the corridors of Building 'B'.  And the entry gables on the North side of Building 'D'.

(Air Doctors) Trim for Building 'C'.  Finished the hard ducts for the North Tower Building 'B' and installed the flex ducts on 1st floor.

(Reliance) Worked on the corridors of Building 'C'.  Wired the fans and can lights in the drops on 1st floor.

(Utek) Framed the drops on 2nd, 3rd and 4th floors in Building 'B'.

(Precision Asphalt) Striped Building 'A' parking lot.