Friday 4/26/2013

Weather: Partly Cloudy 57˚/30˚ 

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (1)
<SBS>                              (3)
<Nutek>                            (9)
<Diamond Z>                    (3)
<Warburtons>                  (8)
<Reliance>                       (3)
<Red Oak>                       (3)

Work in Progress
(Huskies) Dug trenches for the irrigation pipes around Building 'A'. 

(Wall to Wall) Painted 1st floor Building 'B'.  Caulked and filled the South breezeway of Building 'A'. 

(SBS)  Finished Installing trim in the South end of Building 'B' 3rd floor..

(Nutek)  Textured on 3rd, & 4th South floor Building 'B'.  Taped patios and breezeways in Building 'C'&"D'
.
(Diamond Z) Continued the stone on the East Columns and East side of Building 'B'.

(Warburtons) Worked on the West side of Building 'D" entry.  Worked on the patios and breezeway and the South end of Building 'B'.