Wednesday 4/24/2013

Weather: Partly Cloudy 57˚/30˚ 

Subs on Site
<Huskies>                        (4)
<G&M Woods>                 (4)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Nutek>                            (11)
<Diamond Z>                    (3)
<Warburtons>                  (10)
<Reliance>                       (5)
<Clegg Steel>                   (5)
<DG Concrete>                 (3)
<Elite Structures>            (2)

Work in Progress
(Huskies) Dug trenches for the irrigation pipes around Building 'A'. Found the sleeves under the pavement. 

(G&M Woods) Installed cabinets on 4th floor in Building 'E'.

(Wall to Wall) Prepped and primed the North end of 1st floor Building 'B'.

(SBS) Installed blinds and mirrors in Building 'A's rented units.  Finished Installing trim in the South end of Building 'B' 2nd floor..

(Nutek)  Taped on 2nd, 3rd, & 4th floor Building 'B'.  Taped patios and breezeways in Building 'A'.

(Diamond Z) Continued the stone on the East Columns and East side of Building 'B'.

(Warburtons) Worked on the South side of Building 'D" entry.  Worked on the patios and breezeway and the South end of Building 'B'.  Siding on the Club House.


(Reliance) Trim on Building 'E'.

(Clegg Steel) Installed the handrails on the stairs and the chimney caps.

(DG Concrete) Backfilled Building 'D' and built the rock walls around it.

(Elite Structures) Cut the asphalt were their footing will be poured.