Weather: Partly Cloudy 60˚/30˚
Subs on Site
(SBS) Pick-up base in Building 'D'. Installed door frames on the Club House. Installed blinds in Building 'A's rented units..
(Diamond Z) Continued the stone on the East Columns and South end of Building 'B'.
Subs on Site
<G&M Woods> (4)
<Wall to Wall> (3)
<SBS> (2)
<Wall to Wall> (3)
<SBS> (2)
<Nutek> (11)
<Diamond Z> (3)
<Warburtons> (10)
<Reliance> (5)
<DG Concrete> (3)
Work in Progress
(G&M Woods) Installed cabinets in Building 'E'.
(Wall to Wall) Started prepping and primed the North end of 1st floor Building 'B'.
(Wall to Wall) Started prepping and primed the North end of 1st floor Building 'B'.
(SBS) Pick-up base in Building 'D'. Installed door frames on the Club House. Installed blinds in Building 'A's rented units..
(Nutek) Taped on 2nd, 3rd, & 4th floor Building 'B'. Hung the patios and breezeways in Building 'B'.
(Diamond Z) Continued the stone on the East Columns and South end of Building 'B'.
(Warburtons) Finished Building 'C'. Worked on the patios and breezeway on the North end of Building 'B'.
(Reliance) Trim on Building 'E'.
(DG Concrete) Re-dug the meter on the West end of on Building 'E' which was only 3 feet deep on the building side causing the setter to be crooked. Dusty (Maeser) came and Vacuumed the 2' meter cans to replace them with 30" ones for Building 'C'
.
Sub Meeting 4/22/2013
Rick (Warburtons)
Rob (Wall to Wall)
Chris (Nutek)
Jesse (Diamond Z)
Zac (Huskies Landscaping)
Talking Points:
Clean-up: Clean your trash and organize your materials.
Building ‘C’ Handrails and chimney caps Thursday 4/19.
Building ‘D’ Siding complete 4/29.
Building ‘E’ Cabinets install complete 4/25. Electrical trim complete 4/25. Rob (Wall to Wall) walked Building ‘E’ with Rick (Warburtons) to show him the hammer marks on the door trim.
Building ‘B’ Drywall, tape, and texture on the South end of 2nd floor will be complete today 4/22, The remainder of South Tower 4/26. North Tower Complete by 5/3. Chris (Nutek) is going to try to get more tapers on site to finish earlier. Finish work on the 2nd floor North Tower will start tomorrow 4/23. Paint on the 1st floor will be painted by Thursday 4/25.
Club House Siding is to start today Monday 4/22. Rick (Warburtons) asked Jesse (Diamond Z) to mark the heights for the stone.
Landscaping Zac estimates 2 weeks per building. They need to coordinate with Shad (DG Concrete) for installation of sleeves under the sidewalks.
Schedule:
Building ‘C’
Siding Complete today 4/22
Chimney Caps and stair rails 4/23.
Building ‘D’
Plumbing gas lines starts 4/23.
Building ‘E’
Cabinets installed 4/25.
Electrical trim complete 4/25.
Building ‘B’
Texture 2nd floor South complete 4/22.
Finish work Starts 2nd floor South 4/23.
Paint 1st floor 4/22 - 4/25.
Texture 3rd and 4th South tower complete 4/25.