Weather: Partly Cloudy 50˚/22˚
Subs on Site
(Knell) Installed gypcrete on the North Tower of Building 'B'.
(SBS) Started trim on the South end of 1st Floor.
(Diamond Z) Continued the stone South end of Building 'B'.
(Air Doctors) Stocked Furnaces in Building 'E' and worked on 3 of the furnaces in Building 'C' that had something wrong with them. They had to cut holes in units on the 2nd and 4th floors of Building 'C'.
Subs on Site
<G&M Woods> (4)
<Wall to Wall> (3)
<SBS> (4)
<Wall to Wall> (3)
<SBS> (4)
<Knell> (6)
<Nutek> (11)
<Nutek> (11)
<Diamond Z> (3)
<Air Doctors> (7)
<Warburtons> (8)
<Reliance> (5)
Work in Progress
(G&M Woods) Installed cabinets in Building 'E'. I asked Geary to check for damaged cabinets in Building 'C'.
(Wall to Wall) Touch up in Building 'C' South Tower.
(Wall to Wall) Touch up in Building 'C' South Tower.
(Knell) Installed gypcrete on the North Tower of Building 'B'.
(SBS) Started trim on the South end of 1st Floor.
(Nutek) Taped on 2nd, 3rd, & 4th floor Building 'B'.
(Diamond Z) Continued the stone South end of Building 'B'.
(Air Doctors) Stocked Furnaces in Building 'E' and worked on 3 of the furnaces in Building 'C' that had something wrong with them. They had to cut holes in units on the 2nd and 4th floors of Building 'C'.
(Warburtons) Worked on the breezeway and patios on the North end of Building 'B'. They also started on the exterior of Building 'B'. Jose started working on the upper portions of Building 'C' with the lift.
(Reliance) Trim on Building 'E'. Installed the fire panel in Building 'E' and 'B'.