Thursday 4/25/2013

Weather: Partly Cloudy 57˚/30˚ 

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (3)
<SBS>                              (3)
<Nutek>                            (9)
<Diamond Z>                    (3)
<Warburtons>                  (10)
<Reliance>                       (3)
<DG Concrete>                 (3)

Work in Progress
(Huskies) Dug trenches for the irrigation pipes around Building 'A'.  I spoke with Salvador about the s 

(Wall to Wall) Painted 1st floor Building 'B'.  Caulked and filled the South breezeway of Building 'A'. 

(SBS) Installed blinds and mirrors in Building 'A's rented units.  Finished Installing trim in the South end of Building 'B' 2nd floor..

(Nutek)  Textured on 3rd, & 4th South floor Building 'B'.  Taped patios and breezeways in Building 'C'&"D'
.

(Diamond Z) Continued the stone on the East Columns and East side of Building 'B'.

(Warburtons) Worked on the North side of Building 'D" entry.  Worked on the patios and breezeway and the South end of Building 'B'.  Finished siding on the Club House.


(Reliance) Trim on Building 'E'.

(DG Concrete) Fixed the sidewalks around 'C' and the condenser pads..