Weather: Partly Cloudy 54˚/32˚
Subs on Site
<Wall to Wall> (3)
<SBS> (3)
<Nutek> (9)
<Nutek> (9)
<Diamond Z> (3)
<Air Doctors> (3)
<Clegg Steel> (3)
<Warburtons> (8)
<Utek> (1)
<Reliance> (3)
<Air Doctors> (3)
<Clegg Steel> (3)
<Warburtons> (8)
<Utek> (1)
<Reliance> (3)
<Red Oak> (6)
<DG Concrete> (3)
<DG Concrete> (3)
Work in Progress
(Wall to Wall) Prepped and Primed 3rd floor Building 'E'.
(SBS) Unloaded the appliances in Building 'D'.
(SBS) Unloaded the appliances in Building 'D'.
(Nutek) Taped the 1st floor and corridors of Building 'B'. Hung units on the 3rd Floor South Tower of Building 'B'.
(Diamond Z) Installed the stone on the North End of Building 'B' and Started on the East Columns.
(Air Doctors) Replaced the duct tape that failed inspection and started running the flues for the water heaters and furnaces on Building 'C'.
(Clegg Steel) Installed the handrails on the patios for Building 'C'. Quality checked the stairs in Buildings 'B' and 'D'.
(Diamond Z) Installed the stone on the North End of Building 'B' and Started on the East Columns.
(Air Doctors) Replaced the duct tape that failed inspection and started running the flues for the water heaters and furnaces on Building 'C'.
(Clegg Steel) Installed the handrails on the patios for Building 'C'. Quality checked the stairs in Buildings 'B' and 'D'.
(Warburtons) Siding in the corridors of Building 'D'. Siding on the entry on the North West of Building 'C'. Cleaned around the Buildings..
(Reliance) Worked on the trim on Building 'D'. Cut out the pipes for the temp power in Building 'A' and patched the concrete.
(Utek) Framed the entry gable and furred out the walls on Building 'B'.
(Red Oak) Formed all of Building 'B' for corridors and patios.
(Utek) Framed the entry gable and furred out the walls on Building 'B'.
(Red Oak) Formed all of Building 'B' for corridors and patios.
(DG Concrete) Finished working on the details around Building 'A'. Back-filled around Building 'E' and finshed a rock walls in front of Building 'C'