Monday 4/8/2013

Weather: Rain 57˚/28˚ 

Subs on Site
<Sterns>                          (2)
<Wall to Wall>                  (3)
<SBS>                              (3)
<Nutek>                            (9)
<Warburtons>                  (8)
<Reliance>                       (3)
<DG Concrete>                (3)

Work in Progress
(Sterns) Poured the side walks on the East side of Building 'A'.

(Wall to Wall) Prepped 1st and 2nd floor Building 'E'.

(SBS) Installed trim on 4th floor of Building 'E'.  They are waiting for a UPS delivery of hardware in Building 'C'.

(Nutek) Taped the fourth floor patios in Building 'D' Started hanging 1st floor and corridors of Building 'B'.

(Warburtons) Siding in the patios of Building 'B'. Patios on Building 'E'.  Siding on the entry on the North West of Building 'C'.

(Reliance) Worked on the trim on Building 'D'.  

(Utek) Framed the drops on 3rd and 4th floors on North tower in Building 'B'.

(DG Concrete) Started working on the details around Building 'A'.  Dug the water main on the North end of Building 'A' down and had Dusty (Maeser Water) inspect the line.  Dusty asked that they added a sheet of rigid foam on top it and take a picture before they buried it.  



Sub Meeting 4/8/2013

Rick (Warburtons)
Jared (Reliance)
Rob (Wall to Wall)
Chris (Nutek)
Ryan (SBS)

Talking Points:
Clean-up: Clean your trash and organize your materials.
Track out and Mud: Each contractor is responsible for their own track out both into the street and onto our lot.
Building ‘C’  Handrails and chimney caps Thursday 4/11.  Fire alarm install 4/19.
Building ‘D’   Electrical Trim started.  Appliances delivered on 4/11.
Building ‘E’   Finish work on 4th floors by 4/8.  Paint starts 4/8 1st, 2nd, and 3rd floors complete by 4/15.  Cabinets delivered 4/15.  
Building ‘B’ Fire caulk inspection for 2nd, 3rd, and 4th floors on the North Tower will be today.  Drywall, tape, and texture on the 1st floor will be complete on 4/15, South tower by 4/22.
 
Schedule:
Building ‘A’
Sidewalks, Water meter depth, and guardrails.
Building ‘C’
Siding Complete by 4/12 (Weather permitting)
Fire alarm by 4/19
Furnaces and trim 4/15 - 4/19
Building ‘D’
Appliances delivered 4/11
Building ‘E’
Finish Work complete 4/6
Paint 4/8-4/15
Cabinets delivered 4/15
Building ‘B’
Fire caulk inspection North Tower  4/8.
Drywall, tape and Texture 1st floor complete 4/15.
Finish work Starts 1st floor 4/15.
Gypcrete 4/18 - 4/19.