Subs on Site
< Precision Asphalt> (2)
<Green Clean> (2)
<G&M Woods> (5)
<Wall to Wall> (2)
<Wall to Wall> (2)
<Nutek> (10)
<Diamond Z> (3)
<Air Doctors> (4)
<Warburtons> (8)
<Reliance> (3)
<Air Doctors> (4)
<Warburtons> (8)
<Reliance> (3)
<Red Oak> (6)
<DG Concrete> (3)
<DG Concrete> (3)
Work in Progress
(Green Clean) Windows and window frames in Building 'D'.
(Wall to Wall) Painted 3rd & 4th floor Building 'E'.
(G&M Woods) Stocked cabinets in Building 'E'.
(G&M Woods) Stocked cabinets in Building 'E'.
(Nutek) Sanded and swept 1st floor and corridors of Building 'B'. Taped on 2nd floor Building 'B'. Hung the rest of the South Tower of Building 'B'.
(Diamond Z) Continued the stone on the East Columns and South end of Building 'B'.
(Air Doctors) Ran the flues for the water heaters and furnaces on Building 'C'.
(Warburtons) Siding in the corridors of Building 'B'.
(Reliance) Trim on Building 'E'.
(Red Oak) Poured Building 'B' North corridors and patios.
(DG Concrete) Rock walls and Rock window wells around 'C'.
Sub Meeting 4/15/2013
Rick (Warburtons)
Rob (Wall to Wall)
Chris (Nutek)
EJ (Air Doctors)
Talking Points:
Clean-up: Clean your trash and organize your materials.
Track out and Mud: Each contractor is responsible for their own track out both into the street and onto our lot.
Building ‘C’ Handrails and chimney caps Thursday 4/18. Fire alarm install 4/16.
Building ‘D’ Furnaces set this week. Plumbing Trim starts 4/22.
Building ‘E’ Paint complete today. Vinyl tomorrow 4/16. Cabinets install starts 4/17.
Building ‘B’ Drywall, tape, and texture on the 1st floor will be complete today, 4/15. Gypcrete pour South Tower 4/18, North Tower 4/19. There is 500 extra feet of drywall in each of the 16 2x1 units. They asked if we could move the gypcrete back one day, Earl said no. South tower texture will be complete 4/22.
Club House Siding is to start on Monday 4/22. Rick (Warburtons) asked to make sure that the penetrations are ready.
Schedule:
Building ‘A’
Move ins this week.
Building ‘C’
Siding Complete by 4/19 (Weather permitting)
Fire alarm by 4/19
Furnaces and trim 4/15 - 4/17
Building ‘D’
Furnaces set 4/18-4/22.
Plumbing gas lines starts 4/22.
Building ‘E’
Paint Complete 4/15
Cabinets delivered 4/15
Vinyl 4/16.
Cabinets 4/17-4/24.
Building ‘B’
Drywall, tape and Texture 1st floor complete 4/15.
Finish work Starts 1st floor 4/16.
Gypcrete 4/18 - 4/19.
South Tower texture complete 4/22.